§ 3-10.305 — Informal bidding procedures

Thousand Oaks, California, Municipal Code (2026 S-78: current city legislation passed through March 31, 2026) · Thousand Oaks Municipal Code § 3-10.305

Corpus is an independent public-information project, not the official City of Thousand Oaks website. Stable reference: corpuslaw.us/code/9713b45b-e4e0-43c6-af02-d1bd54fa369d

Sec. 3-10.305. Informal bidding procedures.

For those projects which qualify under subsection (b) of Section 3-10.302 for informal bidding, the following procedures shall be used: (a) Bidder List. The City shall maintain a list of qualified contractors, identified according to categories of work or follow alternate procedures as allowed by the PCC Section 22034. Minimum criteria for development and maintenance of the contractors’ list shall be consistent with the CUPCCAA rules. (b) Notice. Unless the product or service is proprietary, all contractors on the City’s list for the category of work being bid shall be emailed a notice inviting informal bids, or an announcement/advertisement shall be placed in all construction trade journals specified in this section, or both such mailing and advertising. The trade journals shall be those identified by CUPCCAA as appropriate for this area. In addition, notice shall be posted on the City’s Purchasing website. (c) Bidder’s Security/Failure to Sign Contract. Bidder’s security shall be prescribed in the notice inviting bids in an amount equal to ten (10%) percent of the amount bid. Bidder’s security shall be either a cash deposit with the City, a cashier’s or certified check payable to the City, or a bidder’s bond. Bid security of unsuccessful bidders to be disposed of securely or returned as necessary by the City. However, the lowest responsive and responsible bidder shall forfeit all or part of their bid security, as may be determined by City Council, upon the bidder’s refusal or failure to execute the contract within ten (10) days after the date of the award of the contract. On the refusal or failure of the lowest responsive and responsible bidder to execute the contract, City Council may award the contract to the next lowest responsive and responsible bidder. (d) Minimum Time Period. All mailing of notices to contractors and announcements/advertisements published in the construction trade journals pursuant to subdivision (b) shall be completed not less than ten (10) calendar days before bids are due. (e) Notice Contents. The notice inviting informal bids shall describe the project in general terms, how to obtain more detailed information about the project, and state the time and place for the submission of bids. (f) Performance/Labor/Materials Bonds. A labor and materials bond, plus a performance bond shall be required, from a surety company licensed to do business in California and acceptable to the City, in amounts equivalent to the total contract amount. (g) Bid Opening Procedure. Sealed bids shall be submitted electronically through the City’s eProcurement portal. Bids shall be opened by the City Clerk’s staff in public at the time and place stated in the notice inviting bids. At that time, a written record and tabulation shall be made of all bids received and shall be available for public inspection for a period of one year after the bid opening. The project manager shall make an analysis of the bids for compliance with bid specifications, and thereafter, make a recommendation for award or rejection. (h) Award. The City Manager shall award the contract or reject the bids. The Purchasing Officer may waive minor bid irregularities. (i) Change Orders. A Change Order shall be used to modify the contract documents regarding contract price, schedule of payments, completion date, plans and specifications, and for unit price overruns and under runs, as specified in the Contract. Work description and justification must relate to the original project and must be work necessary to achieve original scope of project. After a determination that the Change Order and its related costs are merited, the City Manager is authorized to issue Contract Amendments or Change Orders up to the contract contingency as awarded for the individual contract. City Manager may approve Project Change Orders until the contract reaches the informal bid limit as is reflected under PCC Section 22032(b). (j) Bids in Excess of Statutory Amount. If all bids received are in excess of the informal bid limit as is reflected under PCC Section 22032(c), City Council may, by passage of a resolution by a four-fifths (4/5) vote, award the contract up to the amount as is reflected under PCC Section 22034(d) to the lowest responsive and responsible bidder if it determines the cost estimate of the City was reasonable. (§ 4, Ord. 1745-NS, eff. January 9, 2026)

Ask a question about Thousand Oaks law

Corpus searches the Thousand Oaks sections it holds and shows the ones that match, with their citations. Free, no sign-in.