§ 43.8.3 — Submittal, review, and compliance with a waste management plan

Municipal Code, City of Torrance, California · Torrance Municipal Code § 43.8.3

Corpus is an independent public-information project, not the official City of Torrance website. Stable reference: corpuslaw.us/code/f22abea1-e417-4d40-aceb-794faf3d595e

§ 43.8.3: Submittal, review, and compliance with a waste management plan.

a) Documentation. Prior to the issuance of a certificate of occupancy for any covered project, the applicant must submit documentation that it has met the diversion requirement for the project to the Official. This documentation must include the following: 1) Receipts or reports from all disposal and diversion facilities and/or vendors that received material showing the type and weight of the received material, whether the material was landfilled or deconstructed, reused and/or recycled; and 2) Any additional information that the applicant believes is relevant to determining its efforts to comply with this Article; and 3) If the City creates a certified facility program, documentation that a certified facility was used for disposal/recycling for a project will achieve compliance with the requirements of this Article. b) Weighing of C&D Debris. An applicant must make reasonable efforts to ensure that all C&D debris diverted or landfilled is measured and recorded using the most accurate method of measurement available. To the extent practical, all C&D debris must be weighed by measurement on scales. Scales must be in compliance with all regulatory requirements for accuracy and maintenance as set forth by the State of California Bureau of Weights and Measures. For C&D debris for which weighing is not practical due to its small size or to other considerations as determined by the Official, a volumetric measurement will be used. For conversion of volumetric measurements to weight, the applicant must use the standardized conversion rates approved by the City for this purpose. c) Determination of Compliance. The Official will review the information submitted by the applicant and determine whether the applicant has complied with the diversion requirement as follows: 1) Full Compliance. If the Official determines that the applicant has fully complied with the diversion requirement applicable to the project, such compliance will be indicated on the WMP. 2) Noncompliance; Administrative Penalty. If the Official determines that the applicant has not complied with this Article, or the applicant fails to submit the documentation required, then the applicant will be assessed an administrative penalty. The amount of the penalty assessed will be Ten Thousand Dollars ($10,000.00) for demolition projects and Five Thousand Dollars ($5,000.00) for construction and remodeling projects. A project that includes demolition in addition to construction or remodeling will be subject to the demolition penalty amount.

Ask a question about Torrance law

Corpus searches the Torrance sections it holds and shows the ones that match, with their citations. Free, no sign-in.