§ 82-49 — Construction contract performance and payment bonds

Code of Ordinances of the City of Arvada, Colorado (Supp. No. 67: codified through Ordinance No. 4932, enacted May 5, 2026) · Arvada Code of Ordinances § 82-49

Corpus is an independent public-information project, not the official City of Arvada website. Stable reference: corpuslaw.us/code/b2c9e56b-dbcb-49b2-b954-f753e57f4d49

Sec. 82-49. - Construction contract performance and payment bonds.

(a) Bonds. When a construction contract is awarded, the following bonds shall be delivered to the city and shall become binding on the parties upon the execution of the contract: (1) Performance bond. A performance bond satisfactory to the city, executed by a surety company authorized to do business in Colorado or otherwise secured in a manner satisfactory to the city, in an amount equal to 100 percent of the price specified in the contract; and (2) Payment bond. A payment bond satisfactory to the city, executed by a surety company authorized to do business in Colorado or otherwise secured in a manner satisfactory to the city, for the protection of all persons supplying labor and material to the contractor or its subcontractors for the performance of the work provided for in the contract, in an amount equal to 100 percent of the price specified in the contract. (b) Security. In lieu of providing a performance or payment bond, a contractor may provide an unconditional letter of credit for 100 percent of the amount required. Such security must be in a form acceptable to the city attorney. (c) Reduction in amount. If a construction contract is awarded in an amount less than $100,000.00, the director may reduce the amount of the performance and payment bonds or security or waive these requirements entirely if deemed appropriate by the director. For all other performance and payment bonds or security, the city manager may reduce the amount of the performance and payment bonds or security to 50 percent of the contract amount upon a written finding that it is in the best interests of the city to do so. (d) Additional bond requirements. Nothing in this section shall be construed to limit the authority of the city to require a performance bond or other security in addition to those bonds or in circumstances other than those specified in this section.

(Ord. No. 4774, § 1, 8-16-2021)

Ask a question about Arvada law

Corpus searches the Arvada sections it holds and shows the ones that match, with their citations. Free, no sign-in.