§ 9-2-12 — Development Progress Required

Boulder Revised Code 1981 (Supplement167; ordinances effective through July30,2026; five publisher-pending ordinances held); partial · Boulder Revised Code 1981 § 9-2-12

Corpus is an independent public-information project, not the official City of Boulder website. Stable reference: corpuslaw.us/code/917258b9-1260-43c5-aa6f-b58050e9d530

9-2-12. - Development Progress Required.

(a) Three-Year Rule: The applicant must obtain applicable building permit approvals and start construction within three years of the date of the final approval of the site review, use review, or form-based code review. For a use review without construction requiring a building permit, the use must be established within three years of the date of final approval. (1) Phasing: For reviews with phased development established in the development agreement, for each development phase, the applicable building permits must be obtained and construction must be started within three years of the start of the phase, or as modified by the development agreement. (2) Expiration: Failure to comply with the three-year rule shall cause the development approval to expire. For phased development, if an approval for one phase expires, then all successive phases not completed or under construction shall expire. After an approval has expired, any new application for development is subject to all the procedures and standards of this title in effect at the time of such application. (3) Vested Rights: Nothing in this section is deemed to create a vested property right in any applicant; such vested property right may only be created pursuant to the provisions of Section 9-2-20, "Creation of Vested Rights," B.R.C. 1981. (b) Extension: If the applicant requests an extension prior to the expiration of a site review, use review, or form-based code review approval, the city manager may grant an extension of the approval pursuant to the following: (1) The city manager will grant up to two one-year extensions to obtain applicable building permit approvals and start construction or establish the use if the applicant demonstrates that it exercised reasonable diligence and has good cause as to why the extension should be granted. The extension must be requested in writing prior to the expiration of the approval. The first extension extends the approval by one year from the date of final approval. The second extension extends the approval by an additional year and can be requested only after the first extension has been granted and additional progress has been made. (A) Criteria for Demonstrating Reasonable Diligence: An applicant may show that it has exercised reasonable diligence by providing evidence that it has done substantial work towards obtaining building permit approval or starting construction. Such evidence may include, without limitation, drafting plans for building permit or technical document review, applications for building permits or other permits that are required prior to the issuance of building permits, or site preparation and grading. (B) Criteria for Demonstrating Good Cause: An applicant may show good cause as to why an extension should be granted by providing evidence that includes, without limitation, the following: a demonstration of the applicant's ability to obtain building permit approval and start construction within the extension; the extension is needed because of the size of the project or phasing of the development; or that economic cycles and market conditions delayed the building permit approval process and start of construction during the original approval period. (c) Building Permits: Upon issuance of a building permit pursuant to a development review approval, the applicant must adhere to the schedule for construction and inspection as defined in the city building code, Chapter 10-5, "Building Code," B.R.C. 1981. In addition to the provisions of this title, all provisions of the building code regarding expiration and termination of building permits shall apply. (d) Annexations/Six-Month Rule: If an owner of property not located within the city, for which a development review application is approved, fails to annex the property to the city within six months of the date of approval, the approval shall expire unless the approving agency extends the time period, upon a finding of good cause predicated upon a written request of the applicant delivered to the city manager before the expiration of the six-month period. (e) Rescission of Development Approval: If, after use review, special review, site review, Planned Development (PD), Planned Residential Development (PRD), or Planned Unit Development (PUD) approval is granted pursuant to this chapter, the owner of property desires to develop, instead, under the provisions of Chapters 9-6, "Use Standards," 9-7, "Form and Bulk Standards," and 9-8, "Intensity Standards," B.R.C. 1981, the owner may request rescission of such use review, site review, PD, PRD or PUD approval by filing a written request for rescission with the city manager. The manager will grant a rescission if: (1) No building permit has been issued for the development and neither the city nor the developer has taken any actions in detrimental reliance on the terms of the development agreement; (2) For a site review, PD, PRD, or PUD approval, the existing or proposed development complies with all the use, form, and intensity requirements of Chapters 9-6, "Use Standards," 9-7, "Form and Bulk Standards," and 9-8, "Intensity Standards," B.R.C. 1981, and there is no substantial public benefit in maintaining the original approval; or (3) For a use review or special review approval, the rescission will return the property to a use that is allowed by right or as a conditional use and the owner is able to meet all applicable standards for such use under this title. Ordinance Nos. 7577 (2007); 8121 (2016); 8337 (2019); 8523 (2022); 8622 (2024)

Ask a question about Boulder law

Corpus searches the Boulder sections it holds and shows the ones that match, with their citations. Free, no sign-in.