§ 17-38-225 — Building permits required; site development plan revocation

Municipal Code of the City and County of Broomfield, Colorado (Codified through Ordinance No. 2304, adopted May 26, 2026 (Supp. No. 54)) · Broomfield Municipal Code § 17-38-225

Corpus is an independent public-information project, not the official City of Broomfield website. Stable reference: corpuslaw.us/code/52e4174a-dc3a-4b03-8c4f-4190d4b517f6

17-38-225 - Building permits required; site development plan revocation.

(A) Within three years from the date on which a site development plan is approved, the owner is required to apply for and be issued building permits for construction on the property consistent with the site development plan. If the owner is not issued building permits within three years, the city council is authorized to revoke the site development plan as hereinafter provided. (B) The city council is authorized to issue to the owner a notice to show cause why the site development plan should not be revoked for failure by the owner to receive a building permit. After service of the notice to show cause on the owner, the city council shall set a site development plan revocation hearing. Service of the notice shall be by personal service or by certified mail. (C) Prior to a revocation hearing, the city council shall refer the matter to the land use review commission for a public hearing and for a recommendation on revocation of the site development plan. (D) Public notice for a revocation hearing by the city council and by the land use review commission shall be given in accordance with the provisions of chapter 17-52, B.M.C. (E) Within thirty days of the conclusion of the public hearing on a site development plan revocation, the city council may revoke the site development plan by resolution. Such resolution shall be recorded in the county in which the site development plan was recorded. (F) The land use review commission recommendation and the city council decision shall take into consideration the following applicable standards in determining whether to revoke a site development plan: (1) Compliance of the site development plan with the master plan; (2) Compatibility of the site development plan with the surrounding area; (3) The need for the uses in the area included within the site development plan; (4) The effect of the site development plan upon future development of the area; (5) The impact of traffic generated by the site development plan on the neighborhood and the surrounding area; (6) The impact of the site development plan on community facilities in the neighborhood and area, including but not limited to schools, library, police and fire protection, recreation facilities, park lands, and open space; (7) The impact of the site development plan on municipal infrastructure in the area, including but not limited to water service, wastewater service, storm water service, transportation systems, and street systems; and (8) Compliance of the site development plan with the Standards & Specifications for Design and Construction of Public Improvements in force at the time of the revocation hearing. (G) On and after the effective date of this section, site development plans approved by the city council shall include the following notation: "This site development plan may be revoked by the City Council if building permits are not issued to the owner by the City of Broomfield within three years from the date of approval of this site development plan."

(Ord. 1277 §2, 1997; Ord. 1415 §2, 1999; Ord. 1935 §55, 2011) (Ord. No. 2138, § 61, 4-6-21)