Sec. 26-336. - Bypass.
(a) Bypass not violating applicable pretreatment standards or requirements. An industrial user may allow any bypass to occur which does not cause pretreatment standards or requirements to be violated, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to the provision of Subsections (b) and (c) of this Section. (b) Notice. (1) If an industrial user knows in advance of the need for a bypass, it shall submit prior notice to the utility, if possible at least ten (10) days before the date of the bypass. (2) An industrial user shall submit oral notice of an unanticipated bypass that exceeds applicable pretreatment standards to the utility within twenty-four (24) hours from the time the industrial user becomes aware of the bypass. Initial notification shall be followed with a detailed written statement no later than five (5) working days after becoming aware of the violation, providing the following information: a. a description of the discharge and cause of the bypass; and b. the duration of the bypass, including the exact dates and times, or, if the bypass has not been corrected, the anticipated time it is expected to continue, and the steps being taken to reduce, eliminate and prevent recurrence of the bypass. (3) The Utilities Executive Director may waive the written report on a case-by-case basis if the oral report has been received within twenty-four (24) hours. (c) Prohibition of bypass. (1) Bypass is prohibited, and the Utilities Executive Director may take enforcement action against an industrial user for a bypass, unless: a. Bypass was unavoidable to prevent loss of life, personal injury or severe property damage; b. There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventative maintenance; and c. The industrial user submitted notices as required under Subsection (b) of this Section. (2) The Utilities Executive Director may approve an anticipated bypass, after considering its adverse effects, if the Utilities Executive Director determines that it will meet the three (3) conditions listed in Paragraph (1) of this Section.
(Ord. No. 020, 2010, § 13, 7-20-10; Ord. No. 080, 2011, § 1, 9-6-11)
Ask a question about Fort Collins law
Corpus searches the Fort Collins sections it holds and shows the ones that match, with their citations. Free, no sign-in.