Sec. 26-371. - Oversizing.

(a) If the utility requires a developer to install water and sewer mains for a subdivision or development of a size or capacity greater than that necessary to serve the new development, the City shall pay the extra expense caused by the oversizing. (b) In order to obtain oversizing payments from the City, the developer must provide copies of the following: (1) Completed bid forms from at least three (3) qualified contractors with an indication of which contractor was awarded the project. The bid forms must contain the description, estimated quantity and unit price for each item included in the project. Each bid must be genuine and not a collusive or sham bid; (2) The contractor's application for final payment as approved by the developer's engineer; (3) A letter from the developer and/or contractor certifying final payment has been received by the contractor; (4) A letter of acceptance from the City Engineer certifying the water and sewer lines were installed in conformance with City standards and specifications; and (5) Any other information deemed necessary by the Utilities Executive Director. (c) The City will reimburse the developer for a portion of the fees incurred by the developer for engineering services related to the water and sewer line project in accordance with the compensation curves included in American Society of Consulting Engineers Manual No. 45, "A Guide for the Engagement of Engineering Services," and with the rules, regulations, policies and procedures of the utility. The City will not contribute more than the total amount of the fee paid to the engineer by the developer. Prior to payment of any portion of the engineering fees by the City, the developer must provide a copy of the following: (1) An invoice from the developer's engineer for any fees assessed on the project; and (2) A letter from the developer and/or engineer certifying final payment of engineering fees. (d) If the developer has complied with the requirements of the City in installing the water and sewer lines and has supplied to the utility in a timely manner the information required by this Section, the City will pay that proportion of the developer's costs for materials and labor attributable to the oversizing requirement as determined by the Utilities Executive Director in accordance with the following tables: (1) Percentage of costs to be paid by the City for oversizing water mains: Size of main used as basis for oversizing (in inches) | Size of main installed 12" | 16" | 20" | 24" 8 | 30% | 49% | 64% | 72% 12 | — | 30% | 48% | 60% 16 | — | — | 29% | 45% 20 | — | — | — | 23% (2) Percentage of costs to be paid by the City for oversizing sewer mains: Size of main used as basis for oversizing (in inches) | Size of main installed 10" | 12" | 15" | 18" | 21" | 24" 8 | 7% | 14% | 41% | 55% | 65% | 70% 10 | — | 7% | 37% | 51% | 62% | 68% 12 | — | — | 32% | 48% | 60% | 66% 15 | — | — | — | 23% | 41% | 49% 18 | — | — | — | — | 22% | 34% 21 | — | — | — | — | — | 15% (e) The books and records of the developer relating to the costs of water and sewer lines in which the utility is participating shall be open to the City at all reasonable times for the purpose of auditing or verifying such costs.

(Ord. No. 167, 1986, § 1(112-160), 11-4-86; Ord. No. 222, 1998, § 3, 12-15-98; Ord. No. 080, 2011, § 1, 9-6-11)

Ask a question about Fort Collins law

Corpus searches the Fort Collins sections it holds and shows the ones that match, with their citations. Free, no sign-in.