Sec. 26-72. - Failure to get permit; penalty.
If any work requiring a permit is commenced without a permit first having been obtained, the Utilities Executive Director may immediately issue a stop-work order until the proper permit is obtained and the offender shall pay any additional penalties established and determined by the Utilities Executive Director. No building permit may be issued until all utility application requirements have been met.
(Ord. No. 165, 1986, § 1(112-22), 11-4-86; Ord. No. 130, 2002, § 33, 9-17-02; Ord. No. 080, 2011, § 1, 9-6-11)
Ask a question about Fort Collins law
Corpus searches the Fort Collins sections it holds and shows the ones that match, with their citations. Free, no sign-in.