§ 12.04.040 — Application for permit
Municipal Code of Lakewood, Colorado (Supp. No. 15: codified through Ordinance No. O-2026-16, adopted April 27, 2026) · Lakewood Municipal Code § 12.04.040
Corpus is an independent public-information project, not the official City of Lakewood website. Stable reference: corpuslaw.us/code/e2f690eb-53e7-4290-8209-91a7e2d49b39
12.04.040 - Application for permit.
A. It is unlawful for any person to perform work within the public way of the city without obtaining a permit from the city. Any person doing work within the public way of a state highway must obtain a permit from the state and the city. If the state inspects the work in state right-of-way, there will be no charge for the Lakewood permit. If the city inspects the work in state right-of-way, all conditions and fees pertaining to a city permit shall apply. B. In Lakewood, the physical construction of public improvements in new developments is the responsibility of the developer of the land. Ownership of those improvements remains with the developer of the land until acceptance by the city. Any person performing work on those improvements which are within a public way, but prior to acceptance by the city, shall obtain a permit from the city and permission from the owner of the improvements in the public way. The permittee shall be financially responsible to the owner of the improvements to carry out all remedial work necessary to receive acceptance by the city of those improvements. This financial obligation shall apply only to the work in the public way done by the permittee. 1. Public Improvement Agreement Permit. An applicant doing work in the public way which requires a public improvement agreement as required by chapter 14.13 of this Code shall have an approved set of plans and specifications prior to permit application. No work shall be started until the Director has approved the plans, specifications, and permit application, and issued a permit. 2. Annual Permits and Individual Permits. A separate written application for that work done under an annual or individual permit shall be submitted to the Director on a form provided by the city for each individual job. The application shall be submitted at least two days prior to the planned start of work in the public way. Permittees may be required to increase this time up to 14 days when the work consists of more than a single spot excavation. The city may require submission of plans and specifications. No work shall be started until the Director has approved the plans and specifications and permit application, and issued a permit, except as specified in Section 12.04.180.
(Ord. O-94-17 § 4, 1994; Ord. O-82-59 § 1 (part), 1981; Ord. O-71-24 § 5, 1971).
Ask a question about Lakewood law
Corpus searches the Lakewood sections it holds and shows the ones that match, with their citations. Free, no sign-in.