§ 15.02.110 — Public and common/private improvement review, construction and acceptance

Code of Ordinances of the City of Longmont, Colorado (Codified through Ordinance No. O-2026-39, enacted June 23, 2026 (Supp. No. 9)) · Longmont Code of Ordinances § 15.02.110

Corpus is an independent public-information project, not the official City of Longmont website. Stable reference: corpuslaw.us/code/be652537-e766-4314-ae57-7d1c1ab2d467

Sec. 15.02.110. - Public and common/private improvement review, construction and acceptance.

A. Applicability and conditions for approval. 1. Public improvements required. a. All developments that require construction of public improvements, reimbursement for public improvements, or financial participation in existing public improvements shall comply with the requirements of this section. b. Conditions of approval. When a development application includes public improvements, financial reimbursement, or financial participation, development approval shall be conditioned on execution of the public improvement agreement, payment of applicable financial securities, participation costs, and all other fees as outlined in the agreement, satisfaction of water deficits under chapter 14.05, and approval of the public improvement plans. c. Exception. A public improvement agreement may not be required when the city manager or designee determines that the public improvements are minor, and financial reimbursements or financial participation are not required. 2. DRC scope of authority. The DRC shall review and approve all plans and related reports for public improvements, including quantity and cost estimates for those improvements. B. Approval of public improvements plans as one package; phasing. 1. Public improvement plans for the entire subdivision plat, PUD overall development plan, limited use, conditional use, or site plan shall be submitted, approved, and financially secured as required below; however, construction acceptance, financial security, fees, payments, and building permit eligibility may be approved or released according to an approved phasing plan. 2. Any subdivision plat, PUD overall development plan, limited use, conditional use, or site plan requiring public improvements may be divided into public improvement phases provided: a. Such phasing is approved by the DRC and is consistent with any preliminary subdivision plat, PUD overall development plan, limited use, conditional use, or site plan approvals, and consistent with any executed agreements pertaining to the subject property; b. The phasing plan supports a logical sequence of development such that each phase can function independently or sequentially with a prior phase, and the phasing plan is consistent with the proposed phasing on the subdivision plat, PUD overall development plan, limited use, conditional use, or site plan; and c. A phase shall not consist primarily of greenway and/or arterial street right-of-way improvements, unless the city manager or designee determines that it is in the best interest of the city to create such a phase. 3. Amendments to a public improvement agreement. a. Amendments to an approved public improvement agreement shall be at the discretion of the DRC. Amendments shall be limited to phasing adjustments, security adjustments, and building permit eligibility. C. Submittal requirements for public improvements. Final reports and plans for all public improvements shall be submitted to the DRC for review. See administrative manual and city standards for submittal requirements. D. Preparation of the public improvement agreement. 1. Contents of submittal. a. The public improvement agreement shall include all commitments and responsibilities of the city and the applicant with respect to public improvement design, installation, acceptance, and cost participation, and applicable payments and fees. b. The DRC shall prepare the public improvement agreement and then present it to the applicant. c. The applicant shall submit the signed and acknowledged public improvement agreement, along with any applicable payment for consideration and execution by the city as outlined in subsection D.2. below. 2. Final review and approval. a. The director and city manager or designee shall review the agreement for conformance to this development code and other city standards, and if in conformance, forward the agreement to the mayor for execution. b. If the agreement is rejected by the director or city manager or designee, it shall be returned to the DRC for further consideration and negotiation with the applicant. If no settlement is reached with the applicant within 90 days of the director or city manager or designee's original rejection, the applicant may appeal the decision to the city council; otherwise, the development application, including the final public improvement reports and plans, shall be deemed automatically withdrawn. 3. Eligibility for recording. The mayor shall execute the public improvement agreement only after all applicable securities, costs, fees, and payments included in the agreement, and all water deficits, have been satisfied. After execution of the agreement, the review process is complete, and the appropriate documents shall be eligible for signature and recording. E. City fees. The city shall collect city engineering, inspection, and recording fees that are required to ensure the development is constructed in accordance with the approved plans and meets the minimum city standards prior to public improvement agreement recordation, or if tied to a particular phase, prior to start of construction of that phase. The fees shall recover the reasonable actual costs associated with the approval, construction, and inspection of the development and shall include the following amounts, as determined by the city manager or designee: 1. The costs of engineering fees for the work to be performed; 2. The cost of city inspection fees calculated based on the proposed improvements for water, sewer, streets, and storm drainage facilities; and 3. The cost of obtaining, managing, and recording all record drawings and additional documents, such as off-site easements and right-of-way dedications. F. Applicable financial securities. 1. General. The city requires adequate financial securities, in an approved form and manner, such that the public improvements, common areas, and on-site private improvements, including, but not limited to, landscaping, irrigation, and paved parking and amenities, shown in the public improvement plan, final development plan, subdivision plat limited use, conditional use, or site plan shall be installed and fully developed. 2. Form; generally. Financial security shall be furnished in any of the following acceptable forms (performance bonds will not be accepted): a. Cash deposit with the city; b. Irrevocable letter of credit from a banking institution with language stipulating that a draw may occur via fax or email, that said letter of credit shall have an automatic renewal clause, and must be in a form acceptable to the city attorney; or c. Any other financial security determined to be acceptable by the city attorney. 3. Financial security amounts and timing. Financial security amounts for public improvements are based on construction costs and shall be adjusted annually according to a standard engineering cost index. The financial security amounts are set administratively and are calculated as follows: a. Single-family detached subdivisions, single-family attached subdivisions and townhome: amount assessed per acre of land included in the subdivision plat, final development plan, limited use, conditional use, site plan, or approved development phase. The financial security shall be submitted to the city at time of construction acceptance. b. All Other Residential development: amount assessed per dwelling unit included in the subdivision plat, final development plan, limited use, conditional use, site plan, or approved development phase. The financial security shall be submitted to the City prior to the release of a building permit or at time of construction acceptance, whichever comes first. c. Mixed-use development: development containing both residential and nonresidential development in the same structure, amount assessed per acre of land included in the subdivision plat, final development plan, limited use, conditional use, site plan, or approved development phase. The financial security shall be submitted to the City prior to the release of a building permit or at time of construction acceptance, whichever comes first. d. Non-residential development: development without residential units (except for care takers units), amount assessed per acre of land included in the subdivision plat, final development plan, limited use, conditional use, site plan, or approved development phase. The financial security shall be submitted to the City prior to the release of a building permit or at time of construction acceptance, whichever comes first. e. City projects: City projects funded through the budget are exempt from providing financial securities. f. Public Private Partnerships: The City Council, through the approval of a public private partnership or development agreement, may waive or reduce securities according to analysis of the criteria listed in subsection 15.02.090.A.2.b. If financial securities are required, they shall be submitted at the earliest of construction acceptance or building permit based on the development type outlined above in subsections 3.b, 3.c, and 3.d. g. Affordable Housing Projects: A project that provides on-site affordable housing equal to or greater than 12 percent of its units for affordable housing and that qualifies for fee reductions under the affordable housing program will reduce the amount of financial securities required by an amount equal to the percentage of fee reductions. The financial securities shall be submitted at the earliest of construction acceptance or building permit issuance based on development type outlined above in 3a, 3b, and 3c. 4. Revised Financial Securities. Whenever financial securities are renewed or when installation of the public improvements is delayed, or if external factors have caused recent price changes (i.e., inflation) the city may require that the security be updated based on a standard engineering cost index to reflect increases in construction costs over time. 5. System wide improvements. The city at its reasonable discretion may require additional financial security beyond that required in subsection 3 above, in the amount of one hundred percent of the materials and labor for improvements that constitute an integral component of the existing system, including, but not limited to: a. Arterial streets; b. Bridges; c. Primary greenway landscaping, irrigation, and concrete trail; d. Railroad or river crossings; e. Storm drainage facilities that are an extension of the city system, or which provide system-wide benefits to the city; f. Subsurface electric and communications infrastructure; g. Traffic signals and devices; h. Water and sanitary sewer lines that provide system-wide benefits to the city; i. Upgrading of existing public and private improvements necessary for the development to meet city standards, as determined by the city manager or designee. Such additional financial securities will be collected prior to recording of the public improvement agreement, or if tied to a particular phase, prior to start of construction of that phase. 6. Financial security amounts for common and private on-site improvements. Financial security amounts for common and private on-site improvements, which will not be maintained by the city, are required as follows: a. For single-family detached residential developments, securities will be collected at time of construction acceptance based on the following conditions: i. One hundred percent of the cost of materials and labor, plus inspection fees, will be due if all improvements are not installed prior to construction acceptance. ii. Ten percent of the cost of materials and labor for all improvements, plus inspection fees, will be due if all improvements are installed prior to construction acceptance. b. For all other development, the city shall collect 100 percent of the costs of materials and labor, plus inspection fees, for all improvements that are not installed, prior to the issuance of a temporary certificate of occupancy or a final certificate of occupancy. 7. Submittal of financial security. a. Public improvements. All financial security, reimbursement, and participation costs required by subsections 15.02.110.E and F of this code shall be submitted to the city manager or designee and as required below. b. Common or private improvements. All financial security, reimbursements, and participation costs required by section 15.02.110.F.6 of this code shall be submitted to the director prior to construction acceptance for single-family detached developments, and prior to certificate of occupancy for all other developments. G. Improvement installations and cost participation. 1. Intent. To the maximum extent practicable, costs of water and sewer lines, storm drainage facilities, streets, and electric installations should be allocated based on the direct benefits that accrue to the developed area. 2. Cost allocations for oversize installations. The city shall participate in the cost of oversizing installations that benefit the newly developed area, as well as adjacent properties and the community in the circumstances described below: a. Water and sewer lines. i. Applicants shall install, at their cost, new water, and sanitary sewer lines of at least the minimum nominal inside diameter specified below and all larger lines required to serve their own developments or pay a pro rata share of the cost of any existing lines. ii. The minimum line requirements are: Table 2.4: Minimum Water Line Requirements Type of Line | Minimum Inside Diameter Water | 8.0 inches Sanitary sewer | 12.0 inches iii. The city shall participate in the cost of oversizing when it determines that a line larger than the minimum and larger than required for the development is needed to serve adjacent properties. iv. The amount of city participation is based on the certified actual, reasonable construction costs of the oversize line installed, less the city estimate based on local industry guidelines of the cost of the minimum specified line or any larger line needed to serve the development. City participation is subject to available funding and appropriations. v. The city may recover some or all of its costs from other benefiting developers. b. Storm drainage facilities. i. Applicants, at their sole cost, shall install storm drainage facilities at least adequate to accept historic flows onto the land and to discharge flows from the land at historic quantities, rates, and locations, or they must have binding agreements in place for discharge at other quantities, rates, or locations. ii. The city shall participate in the cost of additional improvements that the city determines are required to benefit adjacent territories and the community generally, and may recover some or all of its costs from other benefited developers. iii. The amount of city participation is based on the certified actual, reasonable construction costs, less the city estimate based on local industry guidelines of the cost of the improvements needed to serve the development. City participation is subject to available funding and appropriations. c. Availability of funds. If city funding is not available to participate in oversizing at time of construction, the applicant shall install or construct the properly-sized facility, as determined by the city, and may be reimbursed by the city as funding, including third-party developer participation, becomes available. Any third-party participation shall be addressed separately as third-party developments are approved. Details for reimbursements will be included in the public improvement agreement for the development. 3. Arterial streets. a. The applicant shall install, at their cost, all improvements to arterial rights-of-way required to serve the development. b. The applicant shall be responsible for the cost of one-half of a collector street, as determined by the city manager or designee, for each portion of the development fronting on the arterial street. c. The applicant shall be responsible for the cost of turn lanes, arterial paths, and required landscaping. d. See chapter 14.38, regarding transportation impact fees for arterial streets. 4. Electric facilities. a. Longmont Power and Communications (LPC) shall complete the design, material list, and construction specifications for the electric utility system. b. Applicants are required to pay the costs for all electric work within their developments based on the LPC engineering design and cost estimates calculated according to the existing electric utility rates, rules, and regulations. c. Except as permitted by the public improvement agreement, LPC shall install the electric system. Subject to the public improvement agreement, the applicant may elect to install the subsurface infrastructure associated with the LPC design, including excavation, backfill, compaction, conduit, cable-in-conduit, embedded bases for transformers and junction cabinets, service junction boxes, street light poles or bases, and any other facilities included as subsurface infrastructure in the public improvement agreement. i. The applicant is required to install the subsurface infrastructure according to LPC construction drawings and city standards; and ii. LPC will make the final connections to the utility system necessary to provide electric service. 5. Other required installations. The applicant shall be responsible to pay for or construct all site-specific public improvements which the city manager or designee determines to be necessary as a result of the development. Such improvements may include, but are not limited to, on-site collector and local street construction, acceleration and deceleration lanes, traffic control signage and signals, arterial lighting, drainage facilities, landscaping and sidewalks, and greenways. H. Cost participation in existing improvements. Financial participation by a proposed development in existing public improvements constructed by the city or third parties in and adjacent to the subject site shall be based on the following factors: 1. Whether the proposed development will utilize and be directly benefited by the existing facility; 2. The proportion of land that is the subject of the development application proximate to the public improvement, even if individual blocks, phases, or filings to be developed first are not contiguous to the public improvement; 3. The cost of construction, adjusted by a reasonable construction cost inflation factor; 4. Participation costs shall not generally be required in conjunction with building permits, unless otherwise specified in a previously executed agreement; and 5. Whether other agreements, including agreements between third-parties, clearly demonstrate that cost participation is unnecessary, or all relevant third parties to whom cost participation would be owed confirm in writing that cost participation is unnecessary. Participation in existing improvements shall include, but is not limited to, arterial street participation, traffic signals, utilities, third-party reimbursements, and greenways. Cost participation for existing improvements shall be paid prior to recordation of the public improvement agreement, or if tied to a particular phase, prior to start of construction of that phase. I. Common or private improvements. The applicant shall have all landscaping and other improvements completed in acceptable condition prior to the earliest of the following events: 1. Issuance of a certificate of occupancy within each development phase, except for single-family detached residential subdivisions; 2. The city's final acceptance of public improvements for each development phase; or 3. Transfer of common areas to a property owners' association for maintenance. J. Pre-construction conference required. 1. A pre-construction conference with city staff, the applicant, and the applicant's contractor is required prior to the commencement of construction of any public improvements. The applicant shall schedule the conference through the DRC. The purpose of this meeting is to review: a. The approved public improvement plans; b. City standards and specifications with respect to public improvements; c. City permits needed for construction; and d. The construction inspection process and what is required for construction acceptance. 2. When required landscaping, including right-of-way or primary greenway landscaping, is installed after other public improvements, the applicant may schedule subsequent pre-construction conferences with the city to discuss the plans, permits, and inspection schedule for the landscaping improvements. K. Construction acceptance. 1. Public improvements shall be constructed in strict compliance with the approved plans and current city standards. 2. The applicant shall request construction acceptance from the city after installing the improvements for the development or any phase. 3. Section 15.07.070 requires property or homeowners' associations for some developments. For these developments, the applicant must submit proof that the property encompassed by the development has been annexed into the property or homeowners' association before construction acceptance may be granted for public improvements within the development. If the applicant is seeking construction acceptance for public improvements on only a filing or phase of a development, the annexation need extend only to property within that filing or phase. 4. The city manager or designee shall issue a letter of construction acceptance for the development or applicable phase if it finds the improvements comply with the public improvement agreement and city standards. 5. The applicant shall warrant and be responsible for maintenance and repair of all public improvements that receive construction acceptance for a minimum of one year or until final city acceptance of all public improvements, whichever is later. L. Eligibility for building permits. The city shall not issue building permits until applicable land use approvals are issued, applicable financial securities are in place as outlined in the public improvement agreement, and construction acceptance has been issued for all public improvements within the development or applicable phase. M. Eligibility for early building permits. The city shall not issue early (prior to construction acceptance) building permits unless the request meets the following exceptions: 1. Excluding single-family detached residential developments, all other developments may request early release of buildings permits subject to the following requirements and only if approved on a case-by-case basis by the director, fire marshal, and city manager or designee: a. The timing of construction of the public improvements and buildings; b. Fire safety and emergency access, and the type of construction; c. Any other factors, related to the health, safety, and welfare of the public; and d. Submission of all applicable securities for the development or development phase in which the permit is located. 2. Model homes and sales trailers are allowed subject to approval of a temporary use permit under subsection 15.02.080.C, completion of improvements required in the temporary use permit, and submission of all applicable securities for the development or development phase in which the permit is located. N. Temporary certificate of occupancy. 1. The chief building official may issue a temporary certificate of occupancy for a development, or portion thereof, only when all improvements determined necessary by the city for the health, safety, and welfare of the residents, employees, and customers of the development or applicable phase have been completed. 2. The city may, as a condition for issuing a temporary certificate of occupancy, require the applicant to provide additional financial securities in the amount of 150 percent of the original security amount to ensure construction of the public improvements that have not been completed. The city manager or designee shall consider any risk to the health, safety, and welfare of the public when determining whether to require the additional securities. O. Final acceptance of public improvements. 1. The city manager or designee shall determine whether to grant final acceptance of the public improvements based upon a determination of compliance with city standards. 2. The city shall inspect the public improvements at the end of the warranty period, and the developer shall bring any construction not meeting city standards into compliance within a reasonable time identified by the city. 3. If identified deficiencies are not corrected and accepted within 120 days of the end of the warranty period or city inspection, the city may withhold further building permits or certificates of occupancy for the development or applicable phase. The city may at any time draw on the financial securities to correct the deficiencies. 4. The applicant shall have all public and private landscaping and other required improvements completed in acceptable condition, as determined by the city manager or designee, prior to final acceptance of public improvements. 5. The applicant shall provide the city with record drawings that include designer and contractor certification statements of common areas, pocket parks, and other community facilities. The applicant shall provide a copy of the record drawings to the property owners' association prior to final acceptance. 6. Upon issuance of final acceptance, any remaining financial security shall be released to the applicant, and the city shall thereafter maintain the improvements, except those landscaping improvements to be maintained by the adjacent property owner or a property owners' association, as noted on the public improvement plans. Notice of final acceptance and all releases shall be recorded at the county clerk and recorder's office. 7. If final acceptance is not granted, all future maintenance and repair shall remain the responsibility of the applicant until the city grants final acceptance of the improvements. P. Maintenance repair/replacement securities. To ensure the proper functioning and structural integrity of any public improvement or private on-site improvement (including common areas and pocket parks), the city may require the applicant to furnish a maintenance security in a form acceptable to the city and in an amount of up to 20 percent of the costs of construction or installation. The security shall be required at the time of the final acceptance of public improvements or at the issuance of a certificate of occupancy and shall remain in place for the following periods, or until released by the city: 1. Streets, sidewalks, pavement, and related facilities: a minimum of one year from the date of final acceptance; 2. Utilities, street lighting systems, and related facilities: a minimum of one year from the date of final acceptance; 3. Landscaping and buffers, including common areas and pocket parks: a minimum of one year from the date of final acceptance. Q. Release of securities for public improvements. 1. Financial securities. Financial security as required in Subsection F above shall be retained by the city until the public improvements have been certified as complete, the applicable warranty period has been satisfied, and the city has accepted the improvements for maintenance as demonstrated by the issuance of final acceptance as outlined in subsection O above. a. Upon final acceptance by the city, the remaining financial security shall be released, except as provided elsewhere in this section. b. Final acceptance approval shall be recorded. The city shall record a notice of the city's final acceptance of the public improvements in the county clerk and recorder's office. R. Release of securities for common and private improvements. The applicant shall provide record drawings, including designer and contractor certification statements, and a written notice to the city requesting an inspection when common and private improvements have been completed. When the city determines that the improvements fully comply with the approved construction plans, plat, or site plan, the full amount of financial security shall be released, less the city's costs of administration and inspections. S. Failure to Perform. If a party subject to a public improvement agreement fails to timely perform or complete improvements required under the public improvement agreement or approved public, common, and private improvement plans, or other city standards, the city shall send written notice outlining those deficiencies via certified mail to the Project Manager and any person listed for service of notice on the applicable agreement or plan. This initial notice shall provide at least 30 days for the party to come into compliance, or another reasonable time period as determined by the city according to the needs of the particular project. Failure to come into compliance with the initial notice shall constitute a violation of the Land Development Code as provided by Chapter 15.09 and the owner shall be subject the provisions of that section. T. Forfeiture of security. 1. If a developer fails to properly install all required public improvements or private or common on-site improvements within the relevant timeframes, and fails to come into compliance after the notice provided in subsection S, the city may draw on the security and use the funds to complete the required improvements or otherwise render the development safe. 2. After completing the required improvements, the city shall provide a complete accounting of the reasonable actual expenditures to the developer and, as applicable, refund all unused security deposited (and accrued interest, if applicable), to the developer. If the costs to complete the required improvements are greater than the amount of the security, the city may assess the additional costs to the affected developer or responsible association, which assessment shall constitute a lien upon the property and shall be collected by assessment by Boulder or Weld County in the manner of tax assessments. 3. In addition to forfeiture of security, the city shall be authorized to use those remedies and enforcement powers stated in chapter 15.09 if an applicant fails to install required public improvements, amenities, or private on-site improvements.

(Code 2009, § 15.02.110; Ord. No. O-2023-58, § 1, 10-24-2023; Ord. No. O-2024-20, § 2, 3-26-2024)