§ 4.12.200 — Cost or pricing data

Code of Ordinances of the City of Longmont, Colorado (Codified through Ordinance No. O-2026-39, enacted June 23, 2026 (Supp. No. 9)) · Longmont Code of Ordinances § 4.12.200

Corpus is an independent public-information project, not the official City of Longmont website. Stable reference: corpuslaw.us/code/801204b4-8bc0-495b-b42a-51e7eccf62e2

Sec. 4.12.200. - Cost or pricing data.

A. Substantiation of offered prices. The city, at its discretion, may request factual information reasonably available to the bidder prior to award of a contract to substantiate that the price or cost offered, or some portion of it, is reasonable if the price is not: 1. Based on adequate price competition; 2. Based on established catalogue or market prices; or 3. Set by law or regulation. B. Required submissions relating to change orders or contract modifications. The city may request that a contractor submit cost or pricing data pursuant to the pricing of any change order or contract modification, including adjustments to contracts awarded by competitive sealed bidding, whether or not cost or pricing data was required in connection with initial pricing of the contract. C. Exceptions. The submission of cost or pricing data relating to the pricing of a change order or contract modification is not required when: 1. Unrelated and separately priced adjustments for which cost or pricing data would not be required are consolidated for administrative convenience; or 2. It is determined in writing by the purchasing and contracts manager that the requirements of subsection B of this section may be waived, and the determination states the reasons for such waiver. D. Certification required. A contractor, actual or prospective, required to submit cost or pricing data in accordance with this section, must certify that, to the best of the contractor's knowledge and belief, the cost or pricing data submitted was accurate, complete and current as of a mutually specified date prior to the award of the contract or the pricing of the change order or contract modification. E. Price adjustment provision required. Any contract award, change order or contract modification under which the submission and certification of cost or pricing data are required must contain a provision stating that the price to the city, including profit or fee, will be adjusted to exclude any significant sums by which the city finds that such price was increased because the contractor-furnished cost or pricing data was inaccurate, incomplete or not current as of the date agreed upon between the city and the contractor.

(Code 2009, § 4.12.200; Ord. No. O-2011-25, § 2, 4-26-2011; Ord. No. O-2016-59, § 2, 9-27-2016; Ord. No. O-2023-03, § 2, 1-24-2023)