12.12.230 - Public utility excavations—Permit term.
All permits required by Section 12.12.180 shall expire thirty (30) days after their issuance unless sooner revoked. The contractor will be required to adhere to the full duration of the bond terms stipulated in section 12.12.140.
(Ord. dated 8/5/24)