15.36.010 - Permit to demolish buildings and structures.

A. No person shall demolish any building, structure or part thereof without first obtaining a permit for the particular demolition from the building official, which permit shall be valid for no longer than six months after the date of issue. B. No person shall receive a demolition permit unless he complies with the provisions of all state statutes, the state building code and all city ordinances pertaining to the issuance of such permits. C. No person shall receive a demolition permit unless the applicant thereof obtains from the director of health, and files with the building official, written certification that the premises proposed for demolition are free from rodent infestation. D. 1. It shall be the duty of the director of health, or its designee, when a request for such certification is made, to act within fifteen (15) days to inspect the premises which are the subject of the request, to determine whether the premises are free from rodent infestation. 2. If he finds that the premises are free from rodent infestation, he may certify to that effect. If, however, his inspection discloses a rodent infestation, he shall require the owner of the premises to exterminate the rodents forthwith; and upon receipt of satisfactory evidence by him that the premises have been exterminated he shall then certify that the premises are free from rodent infestation. 3. ALL requests for Rodent-Free Inspection and Certification under the Environmental Health Department shall be subject to a processing fee of one hundred twenty-five dollars ($125.00) per inspection. E. In the event that demolition shall not have been substantially completed within thirty (30) days of the issuance of the certification of the director of health, the owner of the premises shall obtain new certification from the director of health and shall not proceed with the demolition until the certification has been filed with the building official, which new certification shall be valid for a period of thirty (30) days, after which further certification shall be necessary if the demolition shall not have been substantially completed; provided that the requirement for any certification following the first certification may be waived at the discretion of the building official if he shall decide that the premises is unsafe to enter. F. No building owned by the city shall be demolished by the city without first being inspected for asbestos, which asbestos shall be removed before the building may be demolished. The director of health shall be responsible for the enforcement of this subsection. G. Applicant must notify by registered or certified mail, not more than ten days prior to submitting final application to the building official, owners of all adjoining property as listed in the records of the tax assessor of the city adjoining the building(s) to be demolished. H. Any person not in compliance with subsections C through E and G of this section shall be guilty of a violation of this code and is liable to be punished by a fine of one hundred dollars ($100.00) per day, or imprisoned for not more than thirty (30) days, or both, each day to be treated as a separate offense.

(Ord. dated 11/1/93 § 1) (Ord. dated 5/16/16)