For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 27-76 — Inspection of work by city engineer or, if designated, the director of public works or their agent(s); procedure when work does not meet specifications, etc.; permits void when work not performed within certain time; guarantee of work by permittee

Code of Ordinances of the City of New Haven, Connecticut (Supp. No. 31: codified through Ordinance No. 2025-0018, enacted September 11, 2025) · New Haven Code of Ordinances § 27-76

Corpus is an independent public-information project, not the official City of New Haven website. Stable reference: corpuslaw.us/code/3e5392c5-2770-4118-a7b0-11a12f46c8b0

Sec. 27-76. - Inspection of work by city engineer or, if designated, the director of public works or their agent(s); procedure when work does not meet specifications, etc.; permits void when work not performed within certain time; guarantee of work by permittee.

(a) The city engineer or, if designated, the director of public works or, their agent(s) are empowered to inspect, or cause to have inspected, at any time, any or all work being performed under a permit issued under this article. (b) If the city engineer or, if designated, the director of public works or his/her agent believes that the work being performed does not meet the specifications and conditions approved or required, by these articles, the permit or approved work zone traffic and/or pedestrian control plans he/she shall immediately notify the permittee. Upon receiving such notice, the permittee shall immediately commence work to correct such condition, unless the city engineer or director of public works or his/her agent provides for a longer period of time. If the permittee cannot immediately address safety requirements called for in the work zone traffic and/or pedestrian control plan the work zone will be closed by the city engineer, director of public works or their agent/s until such time as safety requriements can be met. Penalties for violations of this article III and applicable sections of article II may be assessed in accordance with section 27-82. (c) All permittees shall conform to the following: (1) The pavement surface shall be disrupted only within the area requiring excavation. (2) Excavations shall be made in open cut. Requests for tunneling require the city engineer's or his/her agent's special permission, and under such additional conditions as he/she may impose. Trenches shall be protected whenever bracing and sheeting is necessary as required by the Occupational Safety and Health Act. All excavated material shall be compactly piled and shall not interfere with public travel to any greater extent than necessary. (3) The area to be excavated shall be precut in a straight line with 90-degree angles at the point of intersection. (4) All edges shall have a clean vertical face. Any structures within the construction site shall be leveled to the adjacent surfaces. (5) The permittee shall backfill and compact all excavations. Backfilling materials and methods shall conform to standard detail regulations as established and promulgated by the city engineer or his/her agent. All shall be backfilled and compacted, or suitably covered to the satisfaction of the city engineer or his/her agent at the end of each workday, unless suitable alternatives have been approved by the city engineer or his/her agent. (6) Temporary patching shall be provided immediately upon backfilling and closing of the excavation or opening. Temporary patch materials and methods shall conform to standard detail regulations as established and promulgated by the city engineer or his/her agent. (7) The permittee shall be responsible for the cost of repairs due to settlement or use of improper backfill material or defective work. Improper backfill shall be re-excavated and temporarily patched in accordance with this article's provisions. (d) If a temporary patch fails within two (2) years of completion, the permittee will be notified and will repair the same within twenty-four (24) hours of notification. Upon failure to comply with this provision, the city engineer or his/her agent may direct the repair to be done and will bill the permittee. The permittee shall be liable for the full expense of such work, and such expense to be paid within forty-five (45) days of billing. Delinquent payments will be charged against the surety bond. (e) Any opening or excavation made without a permit shall be immediately filled and temporarily patched, and a permit immediately obtained. If a permit is unobtainable, the city or its contract representative shall permanently patch such temporary opening or excavation in accordance with this article's provisions. The person making such excavation, and the property owner on whose behalf such excavation is made, shall be liable for the full cost thereof, plus the costs provided for in section 27-72. Penalities for violations of this article III and applicable sections of article II may be assessed in accordance with section 27-84. (f) If no work is performed, all permits shall be voided within three (3) months of issuance. If a permit is voided, the permit fee that is included in the portion of the Code that contains all fees shall be forfeited.

(Code of 1985, § 27-40 Ord. of 10-18-95, § 2; Ord. No. 1426, 9-28-06; Ord. No. 1587, 4-20-09)