§ 2-212 — Contract performance compliance procedures
Code of Ordinances of the City of Boynton Beach, Florida (Codified through Ordinance No. 26-023, enacted July 7, 2026. (Supp. No. 2)) · Boynton Beach Code of Ordinances § 2-212
Corpus is an independent public-information project, not the official City of Boynton Beach website. Stable reference: corpuslaw.us/code/3f47accd-a1e1-4d03-b5a5-745e034bc30d
Sec. 2-212. - Contract performance compliance procedures.
(a) The Finance Department will establish procedures for monitoring and evaluating program performance and compliance. Failure to comply with the small business requirements of an awarded contract may result in suspension or debarment of the businesses or individuals involved in accordance with all applicable articles. Contracts shall provide that the participation plan is binding on the contractor. Project specific goals become elements of performance by the contractor in favor of the City. (b) The contractor shall provide a listing of all subcontractors to be used in the performance of the contract, and subcontractor payment information to the City with each request for payment submitted to the City. The director and the user department shall monitor subcontractor participation during the course of the contract and shall have reasonable access to all contract-related documentation held by the contractor relevant to the contract. (c) After the City and the contractor have executed the contract, the contractor shall not make changes to the participation plan or substitute S/MBEs named in the participation plan without the prior written approval of the City Manager. Unauthorized changes or substitutions shall be a violation of this chapter, and may constitute grounds for rejection of the bid or proposal, termination of the contract for breach, the withholding of payment and/or subject the contractor to contract penalties or other sanctions. When a change is requested: (1) All requests for changes or substitutions of the subcontractors named in the participation plan shall be made to the City Manager on a form provided or approved by the City, and shall clearly and fully set forth the basis for the request. A contractor shall not substitute a subcontractor or perform the work designated for a subcontractor with its own forces or with any other subcontractor unless and until the City Manager approves such substitution in writing. A contractor shall not allow a substituted subcontractor to begin work until both the director and the City's project manager have approved the substitution. (2) The facts supporting the request must not have been known nor reasonably should have been known by either party prior to the submission of the participation plan. The contractor must negotiate with the subcontractor to resolve the problem. If requested by either party, the City shall facilitate such a meeting. Where there has been a mistake or disagreement about the scope of work, the S/MBE can be substituted only where an agreement cannot be reached on commercially reasonable terms for the correct scope of work. (3) The City Manager shall allow changes or substitutions of the subcontractor only on the following bases: a. Unavailability after receipt of reasonable notice to proceed; b. Failure of performance; c. Financial incapacity; d. Refusal by the subcontractor to honor the bid or proposal price or qualifications description; e. Mistake of fact or law about the elements of the scope of work of a solicitation where agreement on commercially reasonable terms cannot be reached; f. Failure of the subcontractor to meet insurance, licensing or bonding requirements; or g. The subcontractor's withdrawal of its bid or proposal or qualifications description. (4) The City Manager shall give written notice to the contractor and the affected subcontractor of the decision whether to permit or deny the proposed change or substitution. (5) Where the contractor has established the basis for the substitution to the satisfaction of the City Manager, or if the City requires the substitution of a subcontractor listed in the participation plan, the contractor shall make good faith efforts to fulfill the participation plan. The contractor may seek the assistance of the City in obtaining a new S/MBE subcontractor. If the project specific goal(s) cannot be reached and good faith efforts have been made, the contractor may substitute with a non-S/MBE. (d) If a contractor plans to hire a subcontractor on any scope of work that was not previously disclosed in the participation plan, the contractor shall obtain the approval of the City Manager to modify the participation plan and must make new good faith efforts to ensure that S/MBEs have a fair opportunity to bid on the new scope of work. (e) Changes to the scopes of work shall be documented by the user department at the time they arise, to establish the reasons for the change and the effect on achievement of the S/MBE goals. (f) If the City Manager determines that the contractor has failed to comply with the provisions of the contract, the City Manager shall notify the contractor in writing of the deficiencies. The contractor shall have fourteen (14) days, or such time as specified in the contract, to cure the deficiencies or establish that there are no deficiencies. If the deficiencies are not cured, the City shall have the right to take all lawful actions.
(Ord. No. 06-080, § 2, 10-17-06)
Ask a question about Boynton Beach law
Corpus searches the Boynton Beach sections it holds and shows the ones that match, with their citations. Free, no sign-in.