Sec. 2-764. - Approval of change orders and contract modifications.

(a) The city manager may approve change orders or contract modifications for supplies and services that do not exceed 25 percent of the original contract amount. (b) The city commission, upon recommendation of the city manager, shall approve change orders or contract modifications that exceed 25 percent of the original contract amount for supplies, services and all change orders and contract modifications for construction. (c) Any contract, change order or modification shall contain a provision that the price to the city shall not be adjusted to include any sums by which the city finds that such price was increased because the cost or pricing information submitted by the contracting party was inaccurate, incomplete or not current. (d) The city manager, after consulting with the city attorney, may rescind an award or terminate a contract that does not exceed $250,000.00 on a single purchase or per annum basis. (e) The city commission, upon recommendation of the city manager, has sole authority to rescind an award or terminate a contract in excess of $250,000.00 on a single purchase or per annum basis.

(Code 2006, § 2-829; Ord. No. 2003-23, § 2(431.4), 7-23-2003; Ord. No. 2005-17, § 2(2-431.4), 8-23-2005; Ord. No. 2005-20, § 2(2-431.3), 9-13-2005; Ord. No. 2008-27, § 2, 10-28-2008; Ord. No. 2026-17, § 2(Att. A), 6-2-2026)