Sec. 62-87. - Permit fees.
(a) Any person desiring to do work on or to make excavations in the streets, parks, parkways, sidewalks, alleys, or easements shall secure a permit therefor from the director of public works. The fee for permits under this division shall be as established in section 1-8. (b) A fee in the amount established by the city commission shall be charged for each re-inspection made due to condemnation of work, or due to the fact that work was not ready at the time inspection was called for, or failure to call for an inspection where required. (c) If it is necessary for a utility company to excavate for emergency repair work, a permit shall be secured by telephoning the public works department as soon as possible and the permit obtained within five working days with presentation of plans to this department. (d) No fee will be charged for fire hydrant installation and fire protection sprinkler systems that comply with the state building and fire prevention codes. (e) An additional fee in the amount established in section 1-8 shall be charged for resubmittal of previously rejected plans.
(Code 1958, § 28-32; Code 1991, § 22-112; Code 2006, § 62-64; Ord. No. 2581, § 1, 9-10-1985; Ord. No. 2810, § 1, 9-27-1988; Ord. No. 2981, § 1, 3-31-1992; Ord. No. 3485, § 1, 8-29-2000; Ord. No. O-2003-15, § 1, 5-20-2003)
Ask a question about Coral Gables law
Corpus searches the Coral Gables sections it holds and shows the ones that match, with their citations. Free, no sign-in.