§ 12-623 — Minimum elevations for tidal flood barriers

Code of Ordinances of the City of Davie, Florida (Codified through Ordinance No. O2026-016, enacted September 3, 2026 (Supp. No. 76)) · Davie Code of Ordinances § 12-623

Corpus is an independent public-information project, not the official City of Davie website. Stable reference: corpuslaw.us/code/7701f1aa-665b-455b-9355-6df491a95b14

Sec. 12-623. - Minimum elevations for tidal flood barriers.

(a) All new or substantially repaired or substantially rehabilitated banks, berms, green-grey infrastructure, seawalls, seawall caps, upland stem walls, or other similar infrastructure shall be designed and constructed to perform as tidal flood barriers. Tidal flood barriers shall have a minimum elevation of five (5) feet NAVD88. Applications for new or substantially repaired or substantially rehabilitated tidal flood barriers submitted prior to January 1, 2035, may be permitted at a minimum elevation of four (4) feet NAVD88, if designed and constructed to accommodate a minimum elevation of five (5) feet NAVD88 by January 1, 2050. (b) All property owners must maintain a tidal flood barrier in good repair. A tidal flood barrier is presumed to be in disrepair if it allows tidal waters to flow unimpeded through or over the barrier and onto adjacent property or public right-of-way. The owner of the tidal flood barrier shall demonstrate progress towards repairing the cited defect within sixty (60) days after receiving a notice of violation from the town, and shall complete repairs within three hundred sixty-five (365) days after receipt of such notice of violation. If the required repair or rehabilitation meets the substantial repair or substantial rehabilitation threshold, no later than three hundred sixty-five (365) days after receipt of the notice of violation, the property owner shall design, obtain permits, cause to be constructed, and obtain final inspection approval of seawall improvements that meet the minimum elevation and design requirements. (c) Tidal flood barriers below a minimum five (5) feet NAVD88 elevation shall be improved, designed, and constructed so as to prevent tidal waters from impacting adjacent property or public right-of-way. Causing, suffering, or allowing the trespass of tidal waters onto adjacent property or public right-of-way is hereby declared a public nuisance. After receiving a notice of violation from the town, the owner shall demonstrate progress toward addressing the cited concern within sixty (60) days and complete the construction of an approved remedy no later than three hundred sixty-five (365) days after receipt of the notice of violation. (d) Tidal flood barriers shall be designed and constructed to prevent tidal waters from flowing through the barrier, while still allowing for the release of upland hydrostatic pressure. (e) To the extent practicable, tidal flood barriers shall be designed and constructed to adjoin immediately proximate tidal flood barriers to close gaps and prevent trespass of tidal water. (f) All tidal flood barriers undergoing substantial repair or substantial rehabilitation shall be constructed along the property's entire shoreline. (g) All tidal flood barriers shall be constructed with natural limerock rip-rap, or other approved habitat enhancement, at the waterward face of the structure. (h) Property owners are encouraged to consider approaches and materials that enhance the biological value of traditional (flat surface) seawalls and flood barriers with the incorporation of living shoreline features, use of hybrid green-grey materials, and the use of biological forms, where practicable. (i) This section shall not be construed to require the installation of a seawall where other flood protection measures serve as an equally effective tidal flood barrier. (j) Tidal flood barriers capable of automatically being elevated in advance of high tides to prevent tidal flooding are permissible, provided that automation cannot require daily human intervention.

(Ord. No. O2022-005, § 2(Exh. A), 3-16-22)

Ask a question about Davie law

Corpus searches the Davie sections it holds and shows the ones that match, with their citations. Free, no sign-in.