§ 26-194 — Procedures for grant or denial of permit
Code of Ordinances, City of Gainesville, Florida (Supp. No. 64, Update 1: codified through Ordinance No. 2024-740, adopted November 6, 2025) · Gainesville City Code § 26-194
Corpus is an independent public-information project, not the official City of Gainesville website. Stable reference: corpuslaw.us/code/0d12b8e2-9f52-4fb4-ade4-166e846db969
Sec. 26-194. - Procedures for grant or denial of permit.
(a) Applicants must submit an application for a permit to the department via email. The date and time of the submittal shall be recorded as the date and time the department receives the email containing the application. (b) Within ten business days from the date of receipt, the director shall review complete applications in the order of receipt. The city shall conditionally grant a permit if the applicant has submitted a complete application that satisfies each of the criteria in the application form. Upon the conditional grant of three permits, the remainder of complete applications will be placed on hold. The director shall notify applicants whose applications have been placed on hold in writing that the director will not review the applications until the three conditionally granted permits have been processed by the university and the city. (c) The conditional grant of a permit by the city is subject to the university's approval of the applicant. The conditionally approved applicant must submit an application to the university to operate its micromobility service on campus. (d) If the university approves the application, the city shall issue the city permit upon the applicant's payment of required fees and proof of insurance and bonds. If the university disapproves the application, the city shall deny the permit. (e) If city denies the permit application, the reason for such denial shall be provided in writing and shall advise that the applicant may correct deficiencies in the application within seven calendar days of the notice of denial without incurring an additional application fee. (f) If a permit is finally denied, the director will proceed to review the next on hold application in the order received.
(Ord. No. 180115, § 1, 12-3-20)
Ask a question about Gainesville law
Corpus searches the Gainesville sections it holds and shows the ones that match, with their citations. Free, no sign-in.