Sec. 30-6.4. - Level of service review.

A. Generally. It is the policy of the city that no development order may be issued unless adequate public facilities are available to serve the project, at adopted LOS standards. The applicant shall provide information to show compliance with the adopted LOS standards and meeting concurrency requirements. In order to ensure that adequate public facilities are available concurrent with the impacts of development on each public facility, the following procedures govern the issuance of development orders. B. Exemptions. Developments that are issued a certificate of concurrency exemption as further provided in this chapter are exempt from the concurrency requirements of this chapter. In addition, the following types of development fall below the threshold for any concurrency review and are deemed automatically exempt: 1. Single-family dwellings (including expansions and remodeling) on lots of record that existed on or before June 10, 1992. 2. Building permits for two-family dwellings (including expansions and remodeling) that: 1) are on lots of record that existed on or before June 10, 1992; or 2) previously have met the concurrency requirements of this chapter. 3. Concept review of a development as specified in article III of this chapter. 4. Zoning verification letters with no associated change of use as specified in article III of this chapter. 5. Lot splits. 6. Changes to a new use allowed under the applicable zoning district that do not involve adding any new square footage or impervious surface. C. Mandatory certification of preliminary development orders. Prior to the final approval of a preliminary development order, as defined in this chapter, the owner/developer of a project shall obtain either a certificate of concurrency exemption, a certificate of preliminary concurrency or a certificate of conditional concurrency reservation. Renewals of approvals for preliminary development orders shall consider the implications for concurrency management. D. Mandatory certification of final development orders. Prior to the approval of a final development order, as defined in this chapter, the owner/developer of a project shall demonstrate that a valid and unexpired certificate of concurrency exemption, certificate of final concurrency or certificate of conditional concurrency reservation exists for the project. A project under consideration for a final development order that has a valid and unexpired certificate of preliminary concurrency and that has not been amended in a fashion to change densities or intensities of use shall be automatically granted a certificate of final concurrency. Renewals of approvals for final development orders shall consider the implications for concurrency management. E. Succession. As long as the original certificate of concurrency exemption, certificate of preliminary concurrency, certificate of final concurrency or certificate of conditional concurrency reservation remains valid and unexpired, it shall serve all subsequent development permits for that specific project. F. Optional review of projects. Any person may submit an application for a concurrency determination at any time. A concurrency determination reserves no capacity and is in no way binding on the city. Applications for a concurrency determination shall contain sufficient data on the project to prepare a concurrency determination. G. Credit for redevelopment, reuse or demolition of existing structure. If an applicant proposes to redevelop, reuse or demolish a building or part of a building as part of the redevelopment of a property and desires to receive public facility impact credits for that portion of the property being redeveloped, reused or demolished in accordance with this section, application shall be made and approved prior to such action. Construction shall commence within the timeframe established in the final development order to obtain the benefits of the credit. The applicant shall provide sufficient information about the previous use of the structure(s) so that credits can be calculated. Credits are not transferable to any other site. In the case of reuse or redevelopment of a building, full credit shall be provided for the existing square footage of the building even if a change of use occurs. However, any additional square footage added to the building or development shall be subject to concurrency and TMP review. H. Applications. 1. Submission of application. Applications for a concurrency determination, certificate of concurrency exemption, certificate of preliminary concurrency, certificate of final concurrency and certificate of conditional concurrency reservation shall be on file in the city. Fees for each type of application are set forth in appendix A (schedule of fees, rates and charges). The application shall consist of such information as needed by the city to determine concurrency status. 2. Limitation of approval. A concurrency determination, certificate of concurrency exemption, certificate of preliminary concurrency, certificate of final concurrency and a certificate of conditional concurrency reservation shall apply only to the specific land uses, densities and intensities based on information provided in the application, and, where applicable, the preliminary and final development orders. All applicants, to the extent required by the city, shall submit such applications for entire projects, rather than portions of projects, except in cases of phased developments. 3. Issuance of certification. After concurrency review has been completed, the city manager or designee shall either approve or deny the application. If denied, the denial shall be in writing and shall include the reasons for denial. If a certificate of conditional concurrency reservation is approved, the approval shall require the payment of the relevant reservation fee or a bond equal to the amount of the reservation fee for reserving capacity, as specified in the executed development agreement. This fee shall be paid within ten working days of the issuance of the certificate of concurrency reservation or the certificate shall be cancelled. In either case, the final development order shall not be issued until the capacity reservation fee is paid. Public facility capacity shall be granted on a first-come, first-served basis, determined as of the date and time a certificate of preliminary concurrency, certificate of final concurrency or certificate of conditional concurrency reservation is issued. 4. Expiration and effect. A certificate of concurrency exemption shall be valid for one year. A certificate of preliminary concurrency and certificate of final concurrency shall be valid for the time period that the appropriate development order is valid and unexpired. If either a preliminary or final development order does not have an expiration date, the certificate of preliminary concurrency or certificate of final concurrency shall expire in one year. A certificate of conditional concurrency reservation shall be valid for the time period reserved in the certificate. A new application for a certificate of preliminary or final concurrency shall be submitted if the project does not continue in good faith. A new fee will be assessed for the resubmittal of an application for a certificate of preliminary or final concurrency.

(Ord. No. 200722, § 10, 4-21-22)