Sec. IV-203. - Concurrency certificate.

(a)

General requirement. A certificate of concurrency shall be required prior to the issuance of any development approval including those determined to be de minimis, except historic designation, comprehensive plan amendment, certificate of appropriateness, zoning text amendments, and street vacations. If a development will require more than one development approval, the issuance of the certificate of concurrency shall occur prior to the issuance of the initial development approval. The director of development services shall be the official signatory of all certificates of concurrency that result from development approvals that require planning board action or zoning approval for the downtown zone districts. The director of development services shall be the official signatory of all certificates of concurrency that result from development approvals that only require issuance of either a zoning approval (not including the downtown zone districts) or building permit.

(b)

De minimis development. If a proposed development relates to land use of such a low intensity as to have a de minimis effect, if any, upon the level of service standards set forth in the Sarasota City Plan, the development shall be exempt from concurrency review as provided below.

(1)

Potable water, wastewater, solid waste, recreation/open space, stormwater management, and public school facilities. Development approvals for single-family dwellings and two-family dwellings shall be deemed de minimis as to all public facilities and services. Development approvals for the addition to or the erection of structures of less than 1,500 square feet utilized for non-residential purposes shall be deemed de minimis.

(2)

Transportation facilities. A de minimis impact is an impact that would not affect more than one percent of the maximum volume at the adopted level of service of the affected transportation facilities as determined by the city, utilizing the generalized two-way peak hour volumes in the most recent edition of the Florida Department of Transportation (FDOT) Multimodal Quality/Level of Service Handbook. No impact will be de minimis if the sum of existing roadway volumes from approved projects on a transportation facility would exceed 110 percent of the maximum volume at the adopted level of service of the affected transportation facility.

(c)

Purpose. The purpose of the certificate of concurrency process is to ensure the existence of sufficient infrastructure to maintain the levels of service adopted in the comprehensive plan which are impacted by the proposed development.

(d)

Application. An applicant for a development approval shall provide the city with all information required by the city so as to enable the concurrency evaluation to be made, this shall include all of the information required in the methodology for calculating projected demand for certificates of concurrency as detailed in appendix A of these regulations. Official copies of the methodology shall be kept on file in the office of the city auditor and clerk and in the department of public works, and shall be available to the general public.

(e)

Minimum requirements for concurrency. In order to obtain a certificate of concurrency, the following conditions applicable to the public facility and service must be satisfied:

(1)

Sanitary sewer, solid waste, drainage, and potable water facilities and supplies:

a.

The development approval is issued subject to the condition that, at the time of the issuance of a certificate of occupancy, the necessary facilities and services are in place and available to serve the new development.

b.

At the time the development approval is issued, the necessary facilities and services are guaranteed in an enforceable development agreement, pursuant to F.S. § 163.3220, or an agreement or development order issued pursuant to F.S. ch. 380, to be in place and available to serve the new development at the time of the issuance of a certificate of occupancy.

c.

Prior to approval of a building permit or its functional equivalent, the city shall consult with applicable water suppliers to determine whether adequate water supplies to serve the new development will be available no later than the anticipated date of issuance by the local government of a certificate of occupancy.

(2)

Parks and recreational facilities:

a.

At the time the development approval is issued, the necessary facilities and services are in place or under actual construction;

b.

A development approval is issued subject to the condition that, at the time of the issuance of a certificate of occupancy, the acreage for the necessary facilities and services to serve the new development is dedicated or acquired by the city, or funds in the amount of the developer's fair share are committed; and

1.

The development approval is issued subject to the conditions that the necessary facilities and services needed to serve the new development are scheduled to be in place or under actual construction no more than one year after the issuance of a certificate of occupancy as provided in the adopted city five-year schedule of capital improvements;

2.

At the time the development approval is issued, the necessary facilities and services are the subject of a binding executed agreement between the city and a contractor which provides that the necessary facilities and services to serve the new development are to be in place or under actual construction no more than one year after the issuance of a certificate of occupancy; or

3.

At the time the development approval is issued, the necessary facilities and services are guaranteed in an enforceable development agreement, pursuant to F.S. § 163.3220 or an agreement or development order issued pursuant to F.S. ch. 380, to be in place or under actual construction no more than one year after issuance of a certificate of occupancy.

(3)

Transportation facilities:

a.

At the time a development approval is issued, the necessary facilities and services are in place or under construction;

b.

At the time a development approval is issued, the necessary facilities and services are the subject of a binding executed agreement between the city and a contractor which provides that the necessary facilities and services to serve the new development are to be in place or under construction no more than three years after the issuance of a certificate of occupancy; or

c.

At the time a development approval is issued, the necessary facilities and services are guaranteed in an enforceable development agreement, pursuant to F.S. § 163.3220 or an agreement or development order issued pursuant to F.S. ch. 380, to be in place or under actual construction no more than three years after issuance of a certificate of occupancy.

d.

If it is determined that no available transportation capacity exists to serve a proposed development, a legally binding proportionate fair share mitigation agreement may be approved in order to meet the transportation concurrency requirement.

(4)

Public school facilities.

a.

For district-wide concurrency service areas:

1.

At the time the residential development order or permit is issued, the necessary facilities and services are in place or under construction; or

2.

A residential development order or permit is issued subject to the conditions that the necessary facilities and services needed to serve the new development are scheduled to be in place or under construction not more than three years after permit issuance as provided in the adopted public school facilities program.

b.

For less than district-wide concurrency service areas: If public school concurrency is applied on less than a district-wide basis in the form of concurrency service areas, a residential development order or permit shall be issued only if the needed capacity for the particular service area is available in one or more contiguous service areas and school capacity is available district-wide as defined in F.S. § 163.3180(13)(e).

c.

If it is determined that no available public school capacity exists to serve a proposed residential development, a legally binding proportionate [fair] share mitigation agreement may be approved in order to meet the public school concurrency requirement.

(f)

Credits. See Appendix A for concurrency calculation methodology.

(g)

Appeals. A denial of a certificate of concurrency may be appealed by the applicant to the planning board. A notice of appeal specifying each and every ground in support of granting the certificate of concurrency shall be submitted by the applicant to the city auditor and clerk's office within 20 days from the date of the written denial of the certificate of concurrency.

(1)

The applicant shall have the burden of proof to establish by the presentation of substantial competent evidence to the planning board:

a.

That there was an error in the technical determination made by the city administration to deny the certificate of concurrency; or

b.

That one or more of the conditions in subsection (e) are satisfied such that the necessary public facilities and services will be available concurrent with the impact of the development.

(h)

Expiration. Except for public school facilities, a certificate of concurrency shall automatically expire simultaneously with the expiration of the development approval to which it applies. In the event that a time extension is granted prior to the expiration of a development approval, then the accompanying certificate of concurrency shall be automatically renewed for the length of the time extension. A certificate of concurrency for public school facilities shall be valid for a period not to exceed two years from final site plan approval. For a finding of available public school capacity to remain valid for a period longer than two years for final site plan approval, a building permit for the development must have been issued prior to the expiration date of a finding of available public school capacity and the building permit must remain valid. The expiration of a finding of available public school capacity shall be cause for a new review of public school capacity for a proposed development.

(Ord. No. 02-4357, 4-29-02; Ord. No. 04-4531, § 3, 6-7-04; Ord. No. 08-4819, § 2(att. 1), 7-21-08; Ord. No. 09-4838, § 2(att. 1), 2-17-09; Ord. No. 18-5243, § 2(Exh. A), 6-4-18; Ord. No. 26-5600, § 2(att. A), 8-3-26)