Sec. 21-91. - Sewer main extensions and capacity upgrades.

(a) Sewer main extensions. (1) Economic feasibility. To determine economic feasibility of an extension, the city will perform an economic analysis to determine if 50 percent of the estimated gross revenue to be derived from the extension over a ten-year period is greater than the cost of the off-site extension. If 50 percent of the estimated gross revenue over the ten-year period is equal to or exceeds the cost, the extension will be considered economically feasible. If 50 percent of the estimated gross revenue over the ten-year period is less than the cost of the extension, the revenue shortage shall be referred to as the "feasibility deficit". When a feasibility deficit exists, the developer, customer to be served, or another third party may pay the feasibility deficit, in which case the project would then be considered economically feasible. Payment of the feasibility deficit shall not qualify for reimbursement. (2) Inside city limits. a. Off-site extensions when economically feasible are made and funded in accordance with the city's capital improvement budget. If a developer requests the sewer extension to be made prior to funding being provided in the city's capital improvement budget and it is deemed economically feasible by the city, the developer may execute a written agreement with the city through which the developer will fund the sewer extension and be reimbursed by the city when funding becomes available. The city may require a developer to build an extension for the city's convenience pursuant to subsection 21-67(b). b. On-site extensions in new developments will be constructed and paid for by the developer. Part of the developer's on-site cost may be eligible for rebate in accordance with section 21-93. The city may require the developer to construct infrastructure of increased capacity or the extension of infrastructure beyond that which is necessary to serve the on-site development. In such cases the city will fund the additional cost for such extensions or increased capacity. (3) Outside city limits. a. Off-site extensions when economically feasible are made and funded in accordance with the city's capital improvement budget. If a developer requests the sewer extension to be made prior to funding being provided in the city's capital improvement budget and it is deemed economically feasible by the city, the developer may execute a written agreement with the city through which the developer will fund the sewer extension and be reimbursed by the city when funding becomes available. The city may require a developer to build an extension for the city's convenience pursuant to subsection 21-67(b). Reimbursement will be made only for the length of the extension between the existing sewer and the point where sewer would be considered available to the developer as determined in accordance with the water and sewer agreement between the city and Leon County as amended from time to time. b. On-site extensions in new developments will be constructed and paid for by the developer. The developer's costs are not eligible for rebate unless the development is annexed into the city limits within three years of approval of the final plat. Any dwelling units that have been connected to the city's water system prior to the effective date of annexation will not be eligible for refunds. c. The city may require infrastructure of increased capacity or the extension of infrastructure beyond that which is necessary to serve the on-site development. In such cases the city will fund the additional cost for such extensions or enhancements. (b) Interim facilities. In the event the city manager or designee will allow an interim pumping station and force main as an alternate to the construction of a gravity main, the developer will pay all costs of such installation with no reimbursement. The city will be the owner and operator of such facilities. (c) Sewer main capacity upgrades for development. Inside or outside the city limits, if a sewer main exists which can serve a parcel and that main is of equal or greater diameter to the city's minimum diameter for sewer mains, and a developer has need for greater capacity, the city will fund the upsizing of the existing main to provide desired capacity if such upsizing is economically feasible. The determination of economic feasibility will be made in the same manner as described in subsection 21-91(a)(1). except that the gross revenue shall be calculated based on the projected sewer sales for the new development only.

(Code 1957, § 34-47; Code 1984, § 25-139(f); Ord. No. 80-O-1772, § 4, 4-22-1980; Ord. No. 81-O-1907, § 1, 9-22-1981; Ord. No. 82-O-2005AA, § 1, 6-22-1982; Ord. No. 82-O-2033, § 1, 9-29-1982; Ord. No. 83-O-2226AA, § 1, 1-10-1984; Ord. No. 16-O-18, § 1, 6-22-2016)