§ 8-44 — Review and approval process to abandon a right-of-way or close a public street

Code of General Ordinances of the City of Tallahassee, Florida (Supp. No. 75: codified through Ordinance No. 25-O-28, enacted December 10, 2025) · Tallahassee Land Development Code § 8-44

Corpus is an independent public-information project, not the official City of Tallahassee website. Stable reference: corpuslaw.us/code/33fd2052-a5b3-4633-a1c4-172b312b9162

Sec. 8-44. - Review and approval process to abandon a right-of-way or close a public street.

(a) Within ten calendar days after an application to abandon a right-of-way or to close a public street has been determined to be complete, notice of the pending application shall be mailed by U.S. Mail to each owner of any parcel which is the subject of the application, to each owner of any property located within 1,000 feet of the subject property, and to the physical address of any property located within 1,000 feet of the subject property. Notice shall also be mailed to registered neighborhood associations within 1,000 feet of the parcel which is subject of the hearing. (b) The property that is the subject of the application shall be prominently posted by the applicant pursuant to the policies and procedures of the growth management department. An application shall not be determined complete until the department has verified that the property is properly posted. (c) The application shall be scheduled for the next available meeting of the development review committee. (d) Public notice. Public notice of the development review committee meeting shall be published at least five calendar days in advance of the hearing in a newspaper publication of regular and general circulation in the city and county. Notice shall also be published in a second newspaper publication in advance of the hearing in accordance with policies adopted by the growth management department. (e) Development review committee review. The development review committee shall review the application at the next regularly scheduled meeting. Each reviewing department shall review the criteria for approval provided in this article; and prepare and submit to the growth management department an itemized list of findings of fact which support its recommendation for approval, approval with conditions, or denial of the application; or request additional material and data determined to be necessary to undertake the required review and continue its review to a date and time certain. The growth management department shall notify the applicant of the development review committee's recommendation within five working days of the decision. The development review committee shall issue a written recommendation with findings of fact to the city commission to approve, approve with conditions, or deny the application. (f) City commission public hearing. After the development review committee makes a recommendation, the planning department shall advertise and schedule the application to be heard at the next available date for public hearing before the city commission. (g) City commission public hearing notification. Notice of the public hearing before the city commission shall be published once at least ten days prior to adoption of the resolution in a newspaper of general circulation in the city. Notice shall also be published in a second newspaper publication in advance of the hearing in accordance with policies adopted by the growth management department. The notice of proposed action shall state the date, time, and place of the meeting; the title of the proposed resolution; and the place or places within the city where the proposed resolution may be inspected by the public. The notice shall also advise that interested parties may appear at the meeting and be heard with respect to the proposed resolution. (h) Criteria for approval. Abandonment of rights-of-way or closure of a public street must be demonstrated to be in the best interest of the general public. Neither abandonment of a right-of-way solely for the purpose of placing it on the tax rolls, nor abandonment of a right-of-way solely to benefit an abutting property owner, is considered to be sufficient to meet the test of "in the best interest of the general public." In order to approve an application for abandonment of a right-of-way or a street closure, the application shall demonstrate that it is in the best interest of the public through compliance with the following: (1) The approval of the application shall not create any safety or public health hazard, including any environmental health hazard; (2) The approval of the application shall not result in the substantial diminishment of access to any existing parcel/lot of record; (3) The approval of the application shall enhance the public health, safety, and welfare; (4) The approval of the application shall not result in the substantial diminishment of access to any publicly maintained facility or infrastructure; (5) The approval of the application shall not create any condition inconsistent with the Tallahassee-Leon County Comprehensive Plan, this Code, or the Long Range Transportation Plan; (6) The approval of the application will not eliminate or preclude a street or bicycle/pedestrian interconnection that the city commission intends to retain; (7) The approval of the application will not eliminate or preclude a bicycle/pedestrian trail that the city commission intends to retain; or (8) The approval shall not adversely affect service access required for any official public safety, utility service, or waste collection service provider; the United States Postal Service; Leon County Schools buses; or, StarMetro. (i) Form of abandonment and closure approvals. Abandonment or closure applications shall be approved by resolution of the city commission. (j) Appeal of a city commission decision pertaining to abandonment of a right-of-way or closure of a public street. A party with standing shall have the right to seek review in circuit court as permitted by law within 30 days from final action on any application resulting in the abandonment of a right-of-way or closure of a public street. (k) Conveyance of abandoned rights-of-way. Upon the abandonment of any right-of-way, that property shall be conveyed by quitclaim deed from the city to abutting landowners or other successors of interest pursuant to F.S. § 177.085. Proof of recording the quitclaim deed shall be put in the abandonment file. (l) Administration. For purposes of the complete implementation of this article, in a manner both fair and efficient, additional administrative procedures may be established by the city manager or the growth management department.

(Ord. No. 09-O-29, § 5, 1-27-2010; Ord. No. 19-O-07, § 4, 4-24-2019)