Sec. 38-42. - Early termination of permit.
If a commercial contractor fails to perform in accordance with this chapter or other applicable ordinances, the director shall have the right to demand, in writing, adequate assurance from the commercial contractor that steps have been taken to rectify the situation. The commercial contractor must, within seven days of receipt of such demand, return to the director a written statement that explains reasons for non-performance or delayed, partial or substandard performance, and provides adequate assurance as to future performance. In the event that the commercial contractor fails to submit a statement satisfactory to the director, the director may revoke the commercial contractor's permit. Such revocation shall become effective 30 days following a notice of revocation to the commercial contractor. Notwithstanding any other provision of this chapter, the right to continue to operate under a permit issued by the city is expressly conditioned upon the commercial contractor's timely payment of permit fees. Continued operation in the city without payment of such fees shall be unlawful. In addition, the city may revoke a permit for nonpayment of fees immediately and without notice.
(Code 1989, § 11-89; Ord. No. 354, § 9, 12-19-1994)
Ask a question about Alpharetta law
Corpus searches the Alpharetta sections it holds and shows the ones that match, with their citations. Free, no sign-in.