Sec. 8-71. - Permit required.
No excavating or trenching shall be performed until a permit or authorization for same has been obtained from the city. Any applicant will be required to acknowledge receipt and understanding of safety requirements before any permit will be issued. All such permits shall be conspicuously posted upon the job site.
(Code 1989, § 5-145; Ord. No. 274, § 5, 4-9-1990)