Sec. 19-5.8. - Change orders and amendments.

(a) For purposes of this Section, the phrase "last approved contract price" shall refer to (1) The "price of the contract," as follows: (A) the total price paid or received under the contract when referencing the purchase, sale, or lease of real or personal property or services on a one-time, project-based, as-needed, or isolated basis; and (B) the total annual price paid or received under the contract when referencing the purchase, sale, or lease of real or personal property or services on an ongoing, multiyear, or continuous basis; (2) As of the later of: (A) the date on which the contract was executed; or (B) the date on which a change order or amendment was last approved by the Macon-Bibb County Commission. (b) The mayor or county manager may approve and execute any change orders or amendments modifying the scope or terms of such contract, or the price of the contract, for purposes that are reasonably and substantially related to the subject of the original contract, in accordance with provisions in this Section, so long as the total contract price, including all proposed change orders or amendments, does not exceed $25,000.00. (c) The mayor may approve and execute any change orders or amendments as needed without receiving additional approval from the Commission in the following circumstances: (1) If the total change in the price of the contract from the last approved contract price is, in the aggregate for all intervening or proposed change orders or amendments, less than twenty percent of the last approved contract price; (2) If any amendment does not affect the price paid or received within any fiscal year under the contract; or (3) If the total contract price, including all proposed change orders or amendments, does not exceed $50,000.00. (d) Except as otherwise provided in this Section, if the total change in the price of the contract from the last approved contract price is, in the aggregate for all intervening or proposed change orders or amendments, greater than twenty percent of the last approved contract price, then no change order or amendment which would cause the total contract price to exceed the limits set forth in this Section shall be valid unless first approved by resolution or ordinance of the Commission. (e) Notwithstanding the preceding paragraphs of this Section, if the Commission has specifically appropriated funds for the express purpose of making a purchase or completing a project, then the mayor may execute any change orders or amendments as needed without receiving additional approval from the Commission, so long as the change orders or amendments executed would not increase the price of the contract beyond the amount of money appropriated that that purpose. (f) Notwithstanding the preceding paragraphs in this Section, the mayor shall not be authorized to execute any change order or amendment under this Section in the following circumstances: (1) If the change order or amendment would cause the price of a contract previously below the dollar threshold, specified in Section 19-10 of this Chapter, at which the approval of the Macon-Bibb County Commission is required, to exceed said threshold, then no change order or amendment shall be valid unless first approved by resolution or ordinance of the Commission. (2) If the change order or amendment would cause the price of a contract to exceed appropriated or budgeted sums available to satisfy all obligations of Macon-Bibb County under the contract for the fiscal year, then no change order or amendment shall be valid unless first approved by resolution or ordinance of the Commission. (3) This section shall not be used to artificially divide any contract in a way that would circumvent Macon-Bibb County, state or federal laws regarding requirements for the use of competitive bidding for the purchase of goods or services. (g) Notwithstanding the preceding paragraphs in this Section, the mayor or county manager may approve and execute any change order without receiving additional approval from the Commission where emergency circumstances are present, and the conditions and procedures set forth in Section 19-5.5 of this Code, relating to emergency procurement, are followed.

(Ord. No. O-21-0084, § 1, 10-19-2021)