7-8-14-040 - Pre-submittal meeting, stormwater concept plan, stormwater management plan, and application requirements.
A. Pre-Submittal Meeting. Before a land development permit application is submitted, an applicant may request a pre-submittal meeting with the City of Marietta. The pre-submittal meeting should take place based on an early step in the development process such as before site analysis and inventory (GSMM Section 2.4.2.4) or the stormwater concept plan (GSMM Section 2.4.2.5). The purpose of the pre-submittal meeting is to discuss opportunities, constraints, and ideas for the stormwater management system before formal site design engineering. To the extent applicable, local and regional watershed plans, greenspace plans, trails and greenway plans, and other resource protection plans should be consulted in the pre-submittal meeting. Applicants must request a pre-submittal meeting with the City of Marietta when applying for a determination of infeasibility through the practicability policy. B. Preparation of the Stormwater Concept Plan. The stormwater concept plan shall be prepared using the minimum following steps: 1. Develop the site layout using better site design techniques, as applicable (GSMM Section 2.3). 2. Calculate preliminary estimates of the unified stormwater sizing criteria requirements for stormwater runoff quality/reduction, channel protection, overbank flooding protection and extreme flood protection (GSMM Section 2.2). 3. Perform screening and preliminary selection of appropriate best management practices and identification of potential siting locations (GSMM Section 4.1). C. Contents of the Stormwater Concept Plan. The stormwater concept plan shall contain: 1. Common address and legal description of the site; 2. Vicinity map; and 3. Existing conditions and proposed site layout mapping and plans (recommended scale of one inch equals 50 feet), which illustrate at a minimum: a. Existing and proposed topography, with a minimum of two-foot contours; b. Perennial and intermittent streams; c. Mapping of predominant soils from USDA soil surveys; d. Boundaries of existing predominant vegetation and proposed limits of clearing and grading; e. Location and boundaries of other natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers and other setbacks (e.g., drinking water well setbacks, septic setbacks, etc.); f. Location of existing and proposed roads, buildings, parking areas and other impervious surfaces; g. Existing and proposed utilities (e.g., water, sewer, gas, electric) and easements; h. Preliminary estimates of unified stormwater sizing criteria requirements; i. Preliminary selection and location, size, and limits of disturbance of proposed BMPs; j. Location of existing and proposed conveyance systems such as grass channels, swales, and storm drains; k. Flow paths; l. Location of the boundaries of the base flood floodplain, future-conditions floodplain, and the floodway (as applicable) and relationship of site to upstream and downstream properties and drainage; and m. Preliminary location and dimensions of proposed channel modifications, such as bridge or culvert crossings. D. Preparation and Contents of the Stormwater Management Plan. The stormwater management plan shall contain the items listed in this part and be prepared under the direct supervisory control of either a registered professional engineer or a registered landscape architect licensed in the state of Georgia. Items 3., 4., 5., and 6. shall be sealed and signed by a registered professional engineer licensed in the state of Georgia. The overall site plan must be stamped by a design professional licensed in the state of Georgia for such purpose. (GSMM Section 2.4.2.7) 1. Natural resources inventory; 2. Stormwater concept plan; 3. Existing conditions hydrologic analysis; 4. Post-development hydrologic analysis; 5. Stormwater management system; 6. Downstream analysis; 7. Erosion, sedimentation, and pollution control plan; 8. BMP landscaping plan; 9. Inspection and maintenance agreement; 10. Evidence of acquisition of applicable local and non-local permits; and 11. Determination of infeasibility, if applicable. E. Existing Stormwater Management Structures. For redevelopment and to the extent existing stormwater management structures are being used to meet stormwater management standards, the following must also be included in the stormwater management plan for existing stormwater management structures: 1. As-built drawings; 2. Hydrology reports; 3. Current inspection of existing stormwater management structures with deficiencies noted; and 4. BMP landscaping plans. F. Application Fee. The fee for review of any land development application shall be based on the fee structure established by the City of Marietta and payment shall be made before the issuance of any land-disturbing activity permit or building permit for the development. G. Application Procedures. Land development applications are handled as part of the process to obtain the land-disturbing activity permit pursuant to Article 7-8-12 or building permit pursuant to Article 7-4-2, as applicable. Before any person begins development on a site, the owner of the site shall first obtain approval in accordance with the following procedure: 1. File a land development application with the City of Marietta on the City of Marietta's form of application with the following supporting materials: a. Stormwater management plan prepared in accordance with Section 7-8-14-040(D). b. Certification that the development will be performed in accordance with the stormwater management plan once approved; c. Preliminary Determination of Infeasibility, as applicable, prepared in accordance with the practicability policy; and d. Acknowledgement that applicant has reviewed the City of Marietta's form of inspection and maintenance agreement and that applicant agrees to sign and record such inspection and maintenance agreement before the final inspection. 2. The administrator shall inform the applicant whether the application and supporting materials are approved or disapproved. 3. If the application or supporting materials are disapproved, the administrator shall notify the applicant of such fact in writing. The applicant may then revise any item not meeting the requirements hereof and resubmit the same for the administrator to again consider and either approve or disapprove. 4. If the application and supporting materials are approved, the City of Marietta may issue the associated land-disturbing activity permit or building permit, provided all other legal requirements for the issuance of such permits have been met. The stormwater management plan included in such applications becomes the approved stormwater management plan.
(Ord. No. 8204, 12/9/2020, § 1)