For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 6.12.6 — Street construction and utilities

Code of the City of Rome, Georgia (Part III) (Codified through Ordinance No. 26-01-02, adopted January 26, 2026. (Supp. No. 28)) · Rome Municipal Code, App. B, art. 6, § 6.12.6

Corpus is an independent public-information project, not the official City of Rome website. Stable reference: corpuslaw.us/code/24e74ebb-10f5-4d31-9869-f060972e8552

6.12.6. - Street construction and utilities.

a. Basic Requirements for All Streets. (1) Grading. (a) All streets, roads and alleys shall be graded to their full width by the developer so that pavement extensions or sidewalks, where required or if installed in the future, can be constructed on the same level plane. (b) Preparation of roadway: Before grading is started the entire area to be paved shall be first cleared of all stumps, roots, brush and other objectionable materials. In all areas to be graded or filled, the developer shall stockpile the topsoil later to be spread in all disturbed areas not paved. (c) Grading shall be accurately done to the lines and grades shown on the plans. Embankments shall be placed in uniform layers not to exceed six inches and compacted to a density of 95 percent of the maximum laboratory dry weight per cubic foot as determined by an approved method. Proofrolling shall be accomplished prior to placement of embankments to detect soft spots. (2) Slopes and Shoulder Improvements. (a) The minimum width for all shoulders from back edge of the curb shall be eight feet. All shoulders shall slope one-fourth inch to the foot toward the roadway. (b) On streets with swale ditch drainage, the shoulders shall slope three-quarters inch to the foot away from the roadway for at least five feet to the drainage channel. (c) When all construction is completed, all slopes and shoulders shall be cleared of all rubbish and shall have a stand of grass to prevent undue erosion, either by sprigging or seeding. (d) If any sections of the subgrade are composed of unsuitable or unstable material, such material shall be removed to the depth directed by the appropriate Public Works Department and replaced with suitable, thoroughly compacted material. (e) When the street is to be used for construction traffic before the paving work is completed, a layer of No. 5 stone can be laid as a traffic surface if the developer so desires. 1) This material shall not be used as part of the base material. 2) It may be worked into the subgrade; or it shall be removed before the base course is set up for paving. 3) Provision shall be made to drain low points in road construction when the final paving surface is delayed. (f) Abutting property shall be suitably sloped to the right-of-way line. (3) Protection of Cut or Fill Slopes. Immediately after grading and filling and re-spreading of topsoil, all areas of disturbed soil shall be fertilized and seeded (or in steep areas sodded or otherwise appropriately treated) with suitable vegetative cover to retard erosion. (4) Installation of Utilities. (a) After grading is completed and approved, the curb lines or edge of pavement lines, as applicable, shall be staked by the developer's Registered Land Surveyor. Before any base is applied, all of the underground utilities—water mains, sewer mains, gas mains, or any other underground utilities, and all service connections related thereto—shall be installed completely and provided throughout the length of the street and across the flat section. Service connections for sanitary sewer and water shall be extended to the right-of-way lines. (b) No private improvements, such as private lawn sprinkler systems, yard lighting, and the like, shall be installed within a public right-of-way except by authorization of the Public Works Director. Such authorization, if issued, shall require the owner to assume all repair costs of the owner's facilities should they become damaged. (5) Preparation of subgrade. Prior to placement of the street base, the subgrade shall be compacted to 95 percent density. (6) Street base, curbing and paving. Street base, curbing and paving shall be installed by the developer in accordance with the requirements and standards of this Development Code. b. Testing Requirements. It is the responsibility of the developer to insure that all required tests are made and reported to the Public Works Department. The cost of all testing and quality control shall be performed at the expense of the developer by qualified testing laboratories. Table 6-13 Testing Requirements Type of Test to be Performed | Minimum Number of Tests | Testing Standards Sub-grade Compaction | Each 500 linear feet of roadway | 95% Max Density ASTM-1557 Field Tests ASTM D-1556 F-2922 and D-2167 Base Compaction | Each 500 linear feet of roadway | 100% Max Density ASTM-1557 Field Tests ASTM D-1556 F-2922 and D-2167 Asphalt Density | Each 1,000 linear feet of roadway | 92% Laboratory Density Asphalt Thickness | Each 500 linear feet of roadway | Deficient in thickness not more than ¼″

Ask a question about Rome law

Corpus searches the Rome sections it holds and shows the ones that match, with their citations. Free, no sign-in.