§ 3.21.11 — Time Limits for Variances
Code of Ordinances of the City of Savannah, Georgia (Division II) (enCodePlus online edition as published 2026-11-20) · Savannah Code of Ordinances, pt. 8, ch. 3., art. 3.0, art. 3.21, § 3.21.11
Corpus is an independent public-information project, not the official City of Savannah website. Stable reference: corpuslaw.us/code/85fc8b98-8930-4968-8a59-525b251030d9
3.21.11 Time Limits for Variances
(a) a. Variances Approved by the Zoning Board of Appeals Approval of a variance pursuant to the provisions of this Ordinance shall become null and void unless the following is completed in the time period specified: (i) i. A variance shall expire after twenty-four (24) months from the date of approval if no development activity in furtherance of the variance has occurred. If a building permit, which relies on the variance, is issued and expires under the terms of this Ordinance, the variance requiring the building permit shall also become null and void at the same time the building permit expires. (b) b. Variances Approved by the Planning Commission A variance shall expire twenty-four (24) months from the date of approval if no development activity in furtherance of the variance has occurred. If a building permit, which relies on the variance, is issued and expires under the terms of this Ordinance, the variance requiring the building permit shall also become null and void at the same time the building permit expires. (c) c. Variances Approved bv the Savannah Downtown Historic District Board of Review A variance shall expire twenty-four (24) months from the date of approval if no development activity in furtherance of the variance has occurred. If a building permit, which relies on the variance, is issued and expires under the terms of this Ordinance, the variance requiring the building permit shall also become null and void at the same time the building permit expires. Approval of a variance pursuant to the provisions of this Ordinance shall be valid for the same time period as provided in Sec. 3.19. Upon the expiration of an approved Certificate of Appropriateness or the subsequent approved development plan or building permit that are consistent with the approved Certificate of Appropriateness, the variance shall become null and void. Commentary: Development activity can refer to applied for or issued demolition permits, applied for or issued building permits, and other site work permits that may be required for a project. ()
(Ord. of 05-14-2020(39), § 1, Ord. of 3-12-2026(11), § 1)
Ask a question about Savannah law
Corpus searches the Savannah sections it holds and shows the ones that match, with their citations. Free, no sign-in.