§ 509.04 — Architectural review process
Code of Ordinances of the City of South Fulton, Georgia (Codified through Ordinance No. 2026-022, enacted July 14, 2026. (Supp. No. 13, Update 2)) · South Fulton Code of Ordinances § 509.04
Corpus is an independent public-information project, not the official City of South Fulton website. Stable reference: corpuslaw.us/code/1b9aaa74-9499-4ef5-bc9e-da8555a93aa0
Sec. 509.04. - Architectural review process.
(a) Prior to issuance of a building permit, the applicant shall submit details of exterior materials, colors, design and architectural features of the proposed building which demonstrate compliance with the design standards set forth in this ordinance. (b) South Fulton staff will review all applications for land disturbance permits, building permits and sign permits for compliance with the standards of this overlay district and upon determination of compliance will provide a Certificate of Endorsement (COE) in the form of signing the formally submitted plans and drawings. (c) Prior to the issuance of a building permit, the community will be allowed ten working days to review and comment. An application which otherwise conforms to applicable codes and regulations shall not be delayed issuance of a building permit for more than ten working days due to this review and comment process. (d) All building plans submitted as an application for a building permit should clearly indicate all of the proposed building materials and colors for each facade in accordance with Section 509.12 and Section 509.13. The plans should clearly show the location and calculate the amount/percentages of all building materials per facade.
Ask a question about South Fulton law
Corpus searches the South Fulton sections it holds and shows the ones that match, with their citations. Free, no sign-in.