§ 24-306 — Submission and approval of stormwater pollution prevention plan and other documents

Code of Ordinances of the City of Cedar Falls, Iowa (Codified through Ordinance No. 3140, enacted March 16, 2026. (Supp. No. 27)) · Cedar Falls Code of Ordinances § 24-306

Corpus is an independent public-information project, not the official City of Cedar Falls website. Stable reference: corpuslaw.us/code/9e639c10-5fa0-4d81-91b7-ffdca067297e

Sec. 24-306. - Submission and approval of stormwater pollution prevention plan and other documents.

(a) No person shall begin work on any site that is the subject of a state NPDES General Permit No. 2 until compliance with this section 24-306 and approval of a SWPPP. (b) An applicant in possession of a state NPDES General Permit No. 2 issued by the IDNR shall submit to the city complete, certified copies of the materials described below, together with all supporting calculations: (1) Applicant's plans, specifications and supporting materials previously submitted to the IDNR in support of applicant's application for the state NPDES General Permit No. 2; (2) Applicant's authorizations issued pursuant to applicant's state NPDES General Permit No. 2; (3) An SWPPP prepared in accordance with this chapter. Every SWPPP submitted to the city: a. Shall comply with all current minimum mandatory requirements for SWPPPs promulgated by the IDNR in connection with issuance of a state NPDES General Permit No. 2, as set out in the IDNR publication entitled, "Iowa Department of Natural Resources NPDES General Permit No. 2, Stormwater Discharge Associated With Industrial Activity For Construction Activities, Effective Date—October 1, 2002, to October 1, 2007," including, but not limited to, "Part IV. Stormwater Pollution Prevention Plans," and as said minimum mandatory requirements are modified from time to time hereafter; b. Shall, if the applicant is required by law to file a joint application form entitled, "Protecting State Waters," the state department of natural resources and U.S. Army Corps of Engineers, comply with all mandatory minimum requirements pertaining to such a joint application; c. Shall comply with all other applicable state or federal permit requirements in existence at the time of application; d. Shall be prepared by the applicant's engineer; and e. Shall include within the SWPPP a signed and dated certification by the applicant's engineer that the SWPPP complies with all requirements of this article. (c) In addition to the SWPPP requirements stated in subsection (b) of this section, which constitute minimum mandatory requirements imposed by the program, every SWPPP submitted to the city shall comply with Statewide Urban Design and Specifications (SUDAS) standard design criteria and the Iowa Construction Site Erosion Control Manual, as such manual and SUDAS may be revised or amended from time to time, including, but not limited to, design, location, and phased implementation of effective, practicable stormwater pollution prevention measures, and shall also: (1) Identify the nature of the construction activity and the potential for sediment and other pollutant discharges from the site; (2) Ensure that stockpiles of soil or other materials subject to erosion by wind or water are covered, vegetated, or otherwise effectively protected from erosion and sedimentation in accordance with the amount of time the material will be on site and the manner of its proposed use; with no stockpiling being allowed in the street; (3) Ensure that, until work on the site has been completed, all construction waste materials shall be disposed of in a dumpster of appropriate size and shall not be permitted to be stockpiled on the site unless in a covered and enclosed structure or trailer; (4) Identify measures and procedures including, but not limited to, best management practices, to reasonably minimize site soil compaction and provide soil quality restoration as specified; (5) Ensure that all temporary erosion and sediment controls shall not be removed until the city has determined that the site has been permanently stabilized with 70 percent perennial cover; (6) Identify methods to prevent sediment damage to adjacent properties and sensitive environmental areas such as water bodies, plant communities, rare, threatened and/or endangered species habitat, wildlife corridors, greenways, and the like; (7) Provide for design and construction methods to stabilize steep or long continuous slopes; (8) Include measures to control the quantity and quality of stormwater leaving a site before, during and after construction; (9) Provide for stabilization of all waterways and outlets; (10) Protect storm sewer infrastructure from sediment loading and/or plugging; (11) Specify precautions to be taken to contain sediment when working in or crossing waters of the state; (12) Ensure stabilization of disturbed areas, including utility construction areas, within five calendar days after the area is no longer actively being worked; (13) Protect outlying roads from sediment and mud from construction site activities, including preventing tracking; (14) Provide for disposal of collected sediment and floating debris; and (15) Ensure that when working near waters of the state, as defined in section 24-224, the specific practices itemized immediately below are utilized: a. During construction: 1. All exposed soil areas with a slope of 3:1 or steeper, and that have a continuous positive slope to waters of the state, shall have temporary erosion protection or permanent cover within three days after the area is no longer actively being worked; all other slopes that have a continuous positive slope to the waters of the state shall have temporary erosion protection or permanent cover within seven days after the area is no longer actively being worked; and 2. Temporary sediment basin requirements shall be used for common drainage locations that serve an area that has five or more acres of soil disturbed at one time; and b. Buffer zone. Provide for the maintenance at all times of an undisturbed buffer zone consisting of not less than 100 linear feet from the waters of the state(including tributaries); exceptions from this requirement for areas, such as water crossings or limited water access, are allowed if the applicant fully documents in the SWPPP the circumstances and reasons that the buffer encroachment is necessary; provided, however, that all potential water quality, scenic and other environmental impacts of these exceptions shall be minimized and documented in the SWPPP for the project. (d) The applicant shall post security for compliance with all requirements imposed by the state NPDES General Permit No. 2 as well as necessary remedial work resulting from violation of any provision of this article in an amount of $100.00 per gross acre for building sites, subdivisions or other developments of five acres or more. This amount shall apply to the maximum acreage of soil that will be simultaneously exposed during the project's construction. Acceptable forms of performance security include the following: (1) Performance bonds in form and content acceptable to the city; or (2) Cash escrow agreement in form and content acceptable to the city. (e) The applicant shall also submit a signed written statement to the city which states as follows: "In addition to the performance security posted with this application, the undersigned applicant hereby agrees to defend, indemnify and hold the city harmless from any and all claims, damages or suits arising directly or indirectly out of any act of commission or omission by the applicant, or any employee, agent, assignee, contractor or subcontractor of the applicant, in connection with applicant's state NPDES General Permit No. 2 and/or Stormwater Pollution Prevention Plan." (f) The city shall send written notification to the applicant of the approval of the applicant's SWPPP within a reasonable time following the applicant's completed submission of all documents and information required under this section and posting of the required security, unless the city has provided to the applicant a written bill of particulars identifying non-complying elements of the application. The city shall not issue approval of the applicant's SWPPP until such non-complying elements of the application have been corrected, and until the application complies with the applicant's state NPDES General Permit No. 2, the requirements of this article, and all other applicable laws and regulations, federal, state and local. (g) For so long as a construction site is subject to a state NPDES General Permit No. 2, the applicant shall promptly provide the city with current information as follows: (1) The name, address and telephone number of the applicant's engineer and any other person on site designated by the owner who is knowledgeable and experienced in erosion and sediment control and who will oversee compliance with the state NPDES General Permit No. 2 and the SWPPP; and (2) The name, address and telephone number of the contractor and/or subcontractors that will implement each erosion and sediment control measure identified in the SWPPP. The applicant's failure to provide current information shall constitute a violation of this article.

(Code 2017, § 27-303; Ord. No. 2595, § 1, 9-11-2006)

Ask a question about Cedar Falls law

Corpus searches the Cedar Falls sections it holds and shows the ones that match, with their citations. Free, no sign-in.