Sec. 24-339. - Requirements for approval of stormwater management plan.

(a) Stormwater management plan. No application for a development shall be accepted unless it includes a plan detailing the stormwater management facility, and the control and management of the runoff and water quality impacts resulting from the development. (b) The stormwater management plan shall: (1) Be prepared by either a licensed professional engineer or registered architect if a site is more than five acres of disturbed area. A site with five acres or less of disturbed area shall be prepared by either a licensed professional engineer, a registered architect (including a registered landscape architect), or a professional in erosion and sediment control, as the applicant's engineer. The applicant's engineer shall be credentialed in a manner acceptable to the city, and shall be referred to in this article as the "applicant's engineer." (2) Indicate whether stormwater will be managed on site or off site, and applicable provisions of the general location and type of BMPs, with clear citations to the Iowa Stormwater Management Manual. (c) The stormwater management plan shall include the following information: (1) A map indicating the location of existing and proposed buildings, roads, parking areas, utilities, structural stormwater management facility and sediment and erosion BMPs. The map shall also clearly show proposed land use with tabulation of the percentage of surface area to be adapted to various uses; drainage patterns; unobstructed 100-year storm overflow routes; locations of utilities, roads and easements; and the limits of clearing and grading. (2) Sufficient engineering analysis to show compliance with the city stormwater requirements, including the following: a. Rainfall events, up to and including 1.25 inches of rain, shall be released at a continuous rate over 24 hours or provide an adequate maintenance and repair agreement to manage this level of rainfall event off site. b. All rainfall events greater than 1.25 inches of rain and up to the 100-year rainfall event shall be released at the rate of the five-year frequency rainfall event on the site as it existed at the time construction commenced. c. If there are reasons why subsection (c)(2)a. or b. of this section cannot be achieved, an applicant may apply for a waiver as provided in section 24-342. (3) A written or graphic inventory of the natural resources present at the site and extending a minimum of 500 feet beyond the limits of the site of the proposed development. A description of the watershed for the project shall include soil conditions, forest cover, topography, wetlands, and other native vegetative areas on the site. (4) The city may also require that the applicant file a conceptual plan to analyze the maximum development potential of a site under existing zoning regulations, regardless of whether the applicant presently intends to develop the site to its maximum potential. (5) For developments occurring on a previously developed site, an applicant shall be required to include existing stormwater runoff discharges. (6) Contact information, including the name and address of the owner of the property, and a list of the owner and addresses of adjacent properties. (7) Topographic base map, consisting of a scalable topographic base map of the site which extends a minimum of 500 feet beyond the limits of the proposed development and which indicates existing surface water drainage including streams, ponds, culverts, ditches, and wetlands; current land uses, including all existing structures; locations of utilities, roads, and easements; and significant natural and manmade features. (8) Hydrologic and hydraulic design calculations for the pre-development and post-development conditions for the five-, ten-, and 100-year rainfall events. Such calculations shall include: a. Description of the design storm frequency, intensity and duration; b. Time of concentration; c. Soil curve numbers or runoff coefficients; d. Peak runoff rates and total runoff volumes for each watershed area; e. Infiltration rates, where applicable; f. Culvert capacities; g. Flow velocities; h. Data on the increase in rate and volume of runoff; and i. Documentation of sources for all computation methods and field test results. (9) If a stormwater management facility depends on the hydrologic properties of soils (e.g., infiltration basins), then a soils report shall be submitted. The soils report shall be based on site boring logs or soil pit profiles. The number and location of required soil borings or soil pit profiles shall be determined based on what is necessary to determine the suitability and distribution of soil types present at the location of the facility. (10) Landscaping and vegetative stabilization shall comply with the city's stormwater requirements and shall prevent impairment of BMPs. (11) A maintenance and repair agreement for all stormwater management facilities (see section 24-341). In the event the applicant and the city agree that the regional stormwater management facility installed by the applicant is to be dedicated to the city, the city shall prepare a dedication agreement on such terms and conditions as the city determines are appropriate, which may include requirements that the applicant pay all installation costs and fees. (12) Proof of the recorded maintenance and repair agreement shall be given to the city. The agreement shall require the following: a. The agreement shall require all benefiting properties to participate in the maintenance and repair of the stormwater management facility; b. Said applicant has accepted such responsibility in a written document and has recorded the document in the county recorder's office under state law; and c. Said applicant understands that this easement shall grant the city the right to correct any maintenance or repair issues not corrected by the applicant with said facility and assess the cost of maintenance and repairs to all benefiting properties as liens to be collected in the same manner as property taxes. (13) Performance bond. The cost of the stormwater management facility shall be included in the amount of the cash escrow or payment and performance bond required under chapter 20. (14) Maintenance bond. The cost of the stormwater management facility shall be included in the amount of the subdivision maintenance bond required to be posted by the developer under chapter 20. (d) The stormwater management plan shall be referred for comments to all other interested agencies including, but not limited to, Iowa Department of Natural Resources (IDNR), Iowa Department of Transportation (IDOT), and the Natural Resources Conservation Services (NRCS), and consideration shall be given to all comments received from such agencies in determining whether the stormwater management plan meets the requirements of this article. (e) No building, land use, or SWPPP permits shall be issued until a stormwater management plan or waiver has been approved by the city. (f) Multiple submissions of the stormwater management plans shall include a summary of the differences in the new stormwater management plan from the stormwater management plan previously submitted.

(Code 2017, § 27-406; Ord. No. 2718, § 1, 9-27-2010; Ord. No. 3078, § 3, 9-3-2024)

Ask a question about Cedar Falls law

Corpus searches the Cedar Falls sections it holds and shows the ones that match, with their citations. Free, no sign-in.