71.09 - SWPPP Requirements.

Every SWPPP submitted to the City in support of a major erosion control permit application: Shall contain complete 24-hour contact information for the site owner and the person in charge of providing and maintaining sedimentation and erosion control for the site. The permittee shall inform the City Stormwater Official within 7 calendar days of any change in this contact information. Shall comply with all current minimum mandatory requirements for a SWPPP promulgated by the Iowa DNR in connection with General Permit No. 2, including those published as Summary Guidance for General Permit No. 2 by the Iowa DNR. The City Stormwater Official may develop policies modifying these requirements for sites with a disturbed area less than one acre. Shall comply with all other applicable state or federal permit requirements in existence at the time of application. Reserved. Shall include a drainage plan prepared according to the Design Standards. The drainage plan shall be accompanied by a drainage report. The drainage report shall at a minimum demonstrate that the design of proposed grading, erosion, and sediment control, if constructed per plan, is not expected to adversely impact adjacent properties. Shall be prepared by a design professional as defined herein; Shall include a signed and dated certification by the person preparing the SWPPP that the SWPPP complies with all requirements of this section; and Shall provide phased erosion control plans for the following development categories: Commercial/Industrial Development Grading Phase Construction Phase Final Stabilization Phase Residential Development Grading Phase Infrastructure Phase Lot Development Phase (Final Stabilization Phase) The SWPPP shall be modified by a design professional (as defined herein) as required in General Permit No. 2. Any modification of the SWPPP shall meet the requirements above. The applicant, or a designated third party, shall be required to utilize the interactive website provided by the City to retain SWPPP documents, document weekly SWPPP inspections, and record all land-disturbing activity, sediment/erosion control practices, and good housekeeping practices. (008-24)

Ask a question about Cedar Rapids law

Corpus searches the Cedar Rapids sections it holds and shows the ones that match, with their citations. Free, no sign-in.