§ 102-372 — Time limit for completion
Municipal Code of the City of Des Moines, Iowa (Supp. No. 38, Update 3: codified through Ordinance No. 16,577, adopted August 24, 2026) · Des Moines Municipal Code § 102-372
Corpus is an independent public-information project, not the official City of Des Moines website. Stable reference: corpuslaw.us/code/441b4c6a-c010-4e2f-89c9-0206fe01276f
Sec. 102-372. - Time limit for completion.
(a) The construction of any driveway approach shall be completed within 30 days after its commencement. However, if weather conditions, other forces of nature or circumstances beyond the control of the permittee make construction within such period impossible, upon written application by the permittee to the city engineer and if such conditions are found to exist, construction shall be completed within 30 days after termination of the conditions, to be determined by the city engineer. (b) Failure to complete construction within the time limit established in subsection (a) of this section shall result in a new permit having to be secured for construction at such location.
(C62, § 54-229.05; O.7371; C75, C79, C85, § 23-224; O.11,583; C91, § 23-224)
Ask a question about Des Moines law
Corpus searches the Des Moines sections it holds and shows the ones that match, with their citations. Free, no sign-in.
