§ 118-204 — Conditions of permission to connect and fees payable

Municipal Code of the City of Des Moines, Iowa (Supp. No. 38, Update 3: codified through Ordinance No. 16,577, adopted August 24, 2026) · Des Moines Municipal Code § 118-204

Corpus is an independent public-information project, not the official City of Des Moines website. Stable reference: corpuslaw.us/code/0676aef8-5aa2-4599-a1f1-636c7887dbc9

Sec. 118-204. - Conditions of permission to connect and fees payable.

Sewer connections referred to in section 118-203 of this division may be permitted or denied by the city manager or such city employee as may be designated by the city manager to exercise such function under direction of the city manager, such permission or denial to be exercised with the aim and purpose that no such connection shall be permitted which will be inconsistent with standards contained in city plumbing and right-of-way occupancy ordinances, which will be inconsistent with objectives of the city with reference to possible future annexation of the area proposed for service, which will or may interfere with orderly extension of trunk lines or laterals at some future date, or which will tend to require the sewer to which connection is sought or the sewer system of the city or the sewage treatment facilities of the city to be burdened beyond their rated capacity and shall wherever and whenever permitted be upon the following conditions precedent: (1) No person shall make any connections to the city sewer system either directly or indirectly without first making application therefor and obtaining a permit to do so from the city manager or his or her designee and paying the fees and connection charges established in this division. (2) No sewer connection permit under circumstances described in section 118-203 of this division shall be issued unless a written application for the issuance of a sewer connection permit is submitted to the city manager or his or her designee. The written application shall state the name and address of the applicant; the nature, location and purpose of the connection; the description showing the dimensions thereof and area in square feet of the property to be served with reference to a properly recorded plat; the date of proposed commencement and the date of proposed completion of the connection, and it shall contain an agreement by the owner of the property binding upon the owner and the owner's successors or assigns to comply with all rules and regulations established regulating the use of the sewer and connections thereto including city ordinances relating to plumbing and street excavations, city ordinances prescribing sewer rental charges as stated or as amended; agreeing to waive any possible future objections to annexation proceedings instituted by the city which might be founded upon such sewer service, unless specifically waived or limited by resolution of the city council; and agreeing to hold the city harmless from any loss, liability or damage resulting from such connections or the use thereof. (3) Failure to apply to the city manager or his or her designee with the information required in subsection (2) of this section shall be sufficient cause to deny issuance of a sewer connection permit. The city manager or his or her designee may refuse to issue the permit provided for in this section to any former permit holder who has intentionally violated the sections of this division relating to sewer connections. (4) One sewer connection shall serve no more than 10,000 square feet of property, without approval of the city council setting an additional fee, as provided in this section. If the area of the property to be served exceeds 10,000 square feet, as shown in the written application for sewer connection permit, the city manager or his or her designee shall deny the application and immediately refer it to the city council. The maximum depth of any area to be served adjacent to a sewer to which property outside the city may connect under this section shall be 175 feet from the street right-of-way line, except those properties adjacent to the East Fourteenth Street sewer, which may be served to a depth of not to exceed 400 feet from the centerline of East Fourteenth Street. Any improvements beyond these limitations shall not be served by city sewer. (5) When the application for connecting to the municipal sanitary utilities is filed with the city manager or his or her designee, the application shall be accompanied by a sewer connection fee as established within this division for the applicable trunk sewer, or where no sewer connection fee is established a sum computed at the rate of $0.015 per square foot of lot area to approximate the cost of extending trunk line sewer service to the near vicinity of the subject property and a further sum computed at the rate of $7.76 per front foot of the property to be served to approximate the cost of extending lateral sewer lines to the near vicinity of such property, which fee shall, however, in no case exceed the equitable portion of the total original cost to the city of extending such sanitary utilities to the near vicinity of the property served. If the property to be served exceeds 10,000 square feet, but is otherwise shown to qualify under this section for permission to connect, the city council may, nevertheless, approve the connection but may charge an additional reasonable and equitable fee proportionate to the fee in this subsection, based upon the area and frontage of the property to be served by the connection. (6) If the fee established in subsection (5) of this section exceeds the equitable portion of the total original cost to the city of extending the sanitary utilities to the near vicinity of the property served, the city manager or his or her designee shall submit the application to the city council, which will make such adjustments as will render the fee reasonable and equitable in the circumstances. If the property owner has an objection to the reasonableness of the sewer connection fee or action of the city manager or his or her designee in computing the fee or denying the application, such owner may file a protest with the city council within ten days after such action or determination of the fee. The city council shall then consider the property owner's objection, and its determination shall be final. (7) Upon receipt of the application in compliance with this section, together with the required fee, the city manager or his or her designee shall issue the sewer connection permit within ten days of the date of filing of such application unless it appears that the proposed connection would be contrary to the best interest of the city for reasons referred to in this section or such application does not comply with the conditions stated in this section.

(C62, § 48-55.03; O.8285; C75, C79, C91, § 21-66; O.15,733)