Sec. 12.5-44. - Change orders.

(a) The City will be bound by and liable for only those change orders executed in accordance with the following provisions: (1) The Purchasing Agent is hereby empowered to execute the following types of change orders without prior approval of the City Council: a. Change orders which do not alter the scope or cost of the project; b. Change orders which result in a reduction in cost, but do not alter the scope or quality of the project; c. Change orders which provide for a substitution of services or goods of similar quality for services or goods specified in the contract. (2) The Purchasing Agent is hereby empowered to execute the following types of change orders without prior approval by the City Council: a. Change orders which result from emergency situations, provided, however, he or she shall report such change orders to the City Council. Emergency situations are defined as: 1. Any clear and present danger or hazard to health, safety or welfare; or 2. Condition that would require the cessation of work on the project, if not immediately executed. b. Change orders which result in an additional project cost not exceeding the greater of ten thousand dollars ($10,000.00) or ten (10) percent of the original project cost; provided however, if the City Council approves a change order approving a new project cost, the ten (10) percent figure shall be measured from the latest contract cost approved by the City Council. c. Change orders which result in an additional project cost exceeding: 1. The greater of ten thousand dollars ($10,000.00) or ten (10) percent of the original project cost, and the resulting project cost does not exceed the administrative purchasing limit, or 2. The greater of ten thousand dollars ($10,000) or ten (10) percent of the latest contract cost approved by the Purchasing Agent, and the resulting project cost does not exceed the administrative purchasing limit. (b) All change orders not included in subsection (1) or (2) of this section shall be effective only after prior approval of the City Council. If such approval is given, the Purchasing Agent is hereby authorized to execute such change orders. (c) For the purposes of this section, the following words shall have the meaning set forth below: (1) "Scope" means the work specified in writing as part of the original request for bids or request for proposals, inclusive of any addendum or amendments which have been incorporated into the contract. (2) "Cost" means the amount obligated to be paid by the City for goods or services or a combination thereof pursuant to a written agreement.

(C.B. No. 2003-081, § 1, 5-6-03; C.B. No. 2018-131, § 2, 8-21-18)