§ 29-508 — South sanitary sewer cost recovery fee

Code of Ordinances of the City of Champaign, Illinois (Codified through C.B. No. 2026-125, adopted August 18, 2026 (Supp. No. 81, Update 1)) · Champaign Code of Ordinances § 29-508

Corpus is an independent public-information project, not the official City of Champaign website. Stable reference: corpuslaw.us/code/464fa1bf-a98b-428c-8d50-ae2523501f1d

Sec. 29-508. - South sanitary sewer cost recovery fee.

(a) Amount of cost recovery fee. Any person applying for an Illinois Environmental Protection Agency (IEPA) Permit for connection to the sanitary sewer system, or applying to the IEPA to construct sanitary sewers that will connect to the sanitary sewer system, which permits shall collectively be referred to in this section as an "IEPA Permit," in the geographic areas described in subsection (b) herein, shall pay a fee, referred to in this section as a "sewer cost recovery fee," in an amount equal to $190.00 times the population equivalence approved by the Urbana and Champaign Sanitary District (UCSD). (b) Service areas. The geographic areas subject to the sewer cost recovery fee shall include the following: Tracts of land being part of sections 28, 29, 32, 33, 34 and 35, Township 19 north, Range 8 east of the 3rd P.M. in Champaign County, Illinois, i.e. more particularly described as follows: Section 28 All of Section 28, except the northeast quarter of Section 28. Section 29 All of Section 29, except the northwest quarter of the northwest quarter of Section 29 and southwest quarter of the southeast quarter of Section 29. Section 32 All of the north half of Section 32, except the following tracts of land: The northeast quarter of the northwest quarter of Section 32; and the northwest quarter of the northeast quarter of Section 32; and the north half of the south half of the northeast quarter of Section 32. Section 33 All of the north half of Section 33. Section 34 All of the north half of Section 34. Section 35 All of the west half of the northwest quarter of Section 35. (c) Payment of the cost recovery fee to the UCSD. The person applying for the IEPA Permit shall pay the sewer cost recovery fee to the UCSD, which fee shall then be submitted to the City, all in accordance with the provisions of the Intergovernmental Agreements approved by the City in Council Bill Nos. 2003-189 and 2004-255. (d) Payment of fee a precondition of permit. The payment of said sewer cost recovery fee shall be a precondition for obtaining the required signatures from the City and the USCD on the IEPA Permit Application in question.

(C.B. No. 2006-167, § 1, 6-20-06)