Sec. 29.5-2.22. - Final approval of grading and drainage work.
Final approval of permitted work shall be a requirement of every permit issued. Request for final inspection shall be submitted to the City Engineer upon completion of work authorized by a grading and drainage permit. If, upon final inspection of the development site, the City Engineer finds that the work has been performed in accordance with the approved application and plans for the work, a written certification to that effect shall be issued. If final inspection reveals otherwise, approval shall not be granted until all deficiencies are corrected.
(C.B. No. 97-265, § 1, 10-7-97)