§ 31-408 — Final plat approval in phases

Code of Ordinances of the City of Champaign, Illinois (Codified through C.B. No. 2026-125, adopted August 18, 2026 (Supp. No. 81, Update 1)) · Champaign Code of Ordinances § 31-408

Corpus is an independent public-information project, not the official City of Champaign website. Stable reference: corpuslaw.us/code/e29fbd14-833d-49e6-b12a-a31ba33dabea

Sec. 31-408. - Final plat approval in phases.

(a) The applicant's request. The applicant may request final plat approval of part of the tract contained in the preliminary plat if: (1) A final plat phasing plan was approved as a waiver from section 31-326 in the Council approval of the preliminary plat; or (2) A final plat phasing plan is approved as a waiver from section 31-507 in the Council approval of the first phased final plat of any part of the tract contained in the preliminary plat. (b) Phasing plan. The final plat phasing plan shall include: (1) The date by which the applicant shall record final plats for the entire tract; (2) The dates by which infrastructures shall be extended to the boundaries of the entire tract; (3) The approximate number of the proposed final plats and general location of each phase. (c) Approval. The Council may approve the final plat phasing plan if the Council finds that such phased approval does not impede the orderly growth of public services and infrastructure necessary to efficiently serve the tract included in the approved preliminary plat and the areas adjacent to the tract served by the same public infrastructure as the tract. The final plat phasing plan may be modified with the approval of any phased final plat and such modification is not required to be approved as a waiver by the Plan Commission. Administrative approval of phasing plan adjustments of less than one (1) year may be made by the Planning Director when, in his/her sole discretion, such adjustments do not negatively impact the development of neighboring tracts by the lack of extension of infrastructure. The Council shall not approve a final plat of a portion of a tract or a final plat phasing plan unless all public improvements required by the regulations which are necessary to serve the portion of the tract for which final plat approval is sought are provided for by the applicant to the same extent as if the plat was for the entire tract. (d) Conditions. The Council may condition a final plat phasing plan on the applicant submitting an agreement to dedicate easements or right-of-way in the same approximate locations as those depicted on the approved preliminary plat for the tract which dedications may be required to provide for the orderly growth of the City. The plan may also require the applicant to repay the costs of constructing infrastructure by the City which the applicant would have been required to construct upon the final plat being recorded. However, the City shall not require an agreement to dedicate easements or right-of-way, as a condition of approval of a final plat phasing plan, if: (1) The area not included within approved and recorded final plats is more than five (5) acres; or (2) The easements or right-of-way required to be dedicated are not within two hundred sixty (260) lineal feet of the boundary of the preliminary plat. (e) Penalty. If a final plat for a portion of a tract is recorded, in accordance with this chapter, the owner of the remainder of the tract included in the preliminary plat shall obtain approval and record a final plat or plats for the remainder of the tract within the time provided for in the final plat phasing plan. If the owner fails to record complete final plats of an entire tract as required by this chapter, the City may seek a fine for such violation in addition to other penalties and actions the City may take to enforce this requirement. Each day shall constitute a separate violation by each owner. Each violation is subject to a fine of up to five hundred dollars ($500.00) per day.

(C.B. No. 2002-040, § 1, 3-5-02)