14A-4-407.6.1 Time period.

The 90-day period begins on the date that a copy of the complete demolition permit application, along with one or more photographs accurately depicting the current condition of the building or structure identified in that application, is submitted by the applicant to the Historic Preservation Division of the Department of Planning and Development.