4-11-1. - APPROVAL OF PLATS.

(A) Procedure for the review and approval of plats of subdivision. New plats of subdivision shall comply with the general procedures and requirements pursuant to Section 6-3-12 of the Zoning Ordinance. (B) Issuance of building permits. No building permit shall be issued, nor shall any construction be undertaken on any lot or parcel of land within the City unless such lot or parcel is shown, in its entirety, on a plat of subdivision recorded in the Office of the Cook County Recorder of Deeds. (C) City Council approval. Any new map, plat, subdivision, consolidation or resubdivision of any block, lot, sublot or part thereof, or any piece or parcel of land shall, before recording the same, be submitted to the City Council for its approval by resolution. Each map, plat, subdivision, consolidation or resubdivision so submitted shall be accompanied by a report of the Directors of Public Works and Utilities, describing the public improvements available or required to serve the parcels shown on such map, plat, subdivision, consolidation or resubdivision. No such map, plat, subdivision, consolidation or resubdivision shall be approved by the City Council unless it conforms with all the applicable ordinances of the City. The City Council may condition any such approval on any/all of the following that it determines is applicable: 1. The applicant's dedication to the City of any land required for public streets, alleyways, and/or other rights-of-way identified in the report of the Directors of Public Works and Utilities; 2. The applicant's granting of easements to the City for all required public utilities infrastructure, including, but not limited to, water and sewer mains, that must be located on applicant's property, as identified in the report of the Directors of Public Works and Utilities; 3. The applicant's execution of a development agreement, in form and content approved by the City, wherein he/she commits to construct, pursuant to City-issued permits, all required public improvements identified in the report of the Directors of Public Works and Utilities, and to transfer ownership of said public improvements to the City after their construction; 4. The applicant's submission to the City of a cash bond or other security in accord with 65 ILCS 5/11-39-3, as amended, in an amount equal to one hundred ten (110) percent of the estimated costs of any required public improvements identified in the report of the Directors of Public Works and Utilities, to ensure their construction. Should the bond or other security become due to expire, and the applicant fail to submit a replacement to the City at least fourteen (14) days prior to the expiration date thereof, the City may draw on said bond or security in accordance with the terms thereof, and use the funds drawn to complete the construction of the aforementioned required public improvements; 5. The applicant's recordation, in the Office of the Cook County Recorder of Deeds, of the resolution approving the submitted map, plat, subdivision, consolidation and/or resubdivision, along with all exhibits thereto. Should any resolution approving a map, plat, subdivision, consolidation and/or resubdivision require the applicant to dedicate land to the City, grant the City an easement(s), and/or construct and transfer ownership of public improvements to the City, the City may accept said dedication(s) of land, easement(s), and/or ownership of public improvements by ordinance(s). (D) Survey prerequisite; owner's responsibility. No plat, map or subdivision of any block, lot, sublot or part thereof, or any piece or parcel of land shall be approved by the City Council until the same shall be properly certified by a surveyor and acknowledged by the owner as provided by the general laws of the State of Illinois; and until the owner shall swear or affirm that he/she is the owner in fee of the property described in such plat; and until the same shall have been approved by the Director of Public Works, Director of Utilities, Corporation Counsel and Director of Community and Economic Development.

(Code 1957, §§ 42-109, 42-110; Ord. No. 13-O-63; Ord. No. 31-O-11, § 2, 5-9-2011; Ord. No. 8-O-12, (48-O-11(exh. A, § 4-11-1)), 1-23-2012; Ord. No. 63-O-22, § 8, 8-8-2022)