§ 8-183 — Time within which investigation and recommendations to be made
Code of Ordinances, City of Joliet, Illinois (Supp. No. 201: codified through Ordinance No. 18888, enacted September 1, 2026) · Joliet City Code § 8-183
Corpus is an independent public-information project, not the official City of Joliet website. Stable reference: corpuslaw.us/code/1d659aae-985c-49d4-8529-bec0695ef9bd
Sec. 8-183. - Time within which investigation and recommendations to be made.
The investigation and recommendation required by this division shall be made and completed no later than thirty (30) days after a building permit for such a facility is applied for and the recommendation shall be submitted to the city council no later than fifteen (15) days after the completion of the investigation.
(Ord. No. 5309, § 2, 3-18-69; Ord. No. 7456, § 2(C)(3), 1-6-81)