§ 7-1-13 — PLATTED SETBACKS AND BUILDING LINES:
Municipal Code of Naperville, Illinois (Supp. No. 101: codified through Ordinance No. 26-049, adopted May 19, 2026) · Naperville Municipal Code § 7-1-13
Corpus is an independent public-information project, not the official City of Naperville website. Stable reference: corpuslaw.us/code/3ec65ec2-beb3-49ed-81b8-ea951188d81d
7-1-13: - PLATTED SETBACKS AND BUILDING LINES:
1. Requirements: All building and setback lines shown on recorded plats of subdivision shall be presumed to be reflective of the City Council's intent. Where a platted building or setback line is in conflict with the required yard provisions of Title 6, "Zoning Regulations", of this Code, the more restrictive requirement shall apply. 2. Relief: Property owners may seek relief from a platted building or setback line in accordance with the following: 2.1. Where a platted building or setback line is the same as the required yard for a subject property pursuant to Title 6, "Zoning Regulations", of this Code, the property owner shall only be required to seek approval of a variance to the zoning regulations and shall not be required to obtain approval of a platted setback deviation as prescribed herein. 2.2. Where a platted building or setback line is greater than the required yard for a subject property pursuant to Title 6, "Zoning Regulations", of this Code, the property owner shall be required to seek approval of a deviation to the subdivision regulations, which shall be processed in accordance with Subsection 7-1-8:2 (Subdivision Deviations). 2.3. The City Council may grant a deviation from the platted building or setback line of a recorded subdivision plat if it finds that the variance requested is in harmony with the intent and character of the subdivision, is consistent with the standards of applicable zoning regulations, and complies with all the standards for deviations established herein. 2.4. Required Notice: The petitioner shall post notice of the public meeting on a sign upon the property for which the deviation is requested. Said sign shall comply with the following: 2.4.1. Be a minimum size of three (3) feet by four (4) feet. 2.4.2. Include a title (i.e., "Notice of Public Meeting"); the case number assigned to the application; a brief description of the nature of the request; the date, time and location of the public meeting; and the address and phone number of the City where additional information may be obtained. 2.4.3. Include lettering a minimum of four (4) inches high in the title, and a minimum of two (2) inches high for all other lettering. 2.4.4. Be posted on the property for a continuous period of not more than thirty (30) days and not less than fifteen (15) days in advance of the public meeting. 2.4.5. Be printed on a white background. The lettering for the title on the sign shall be red and all other lettering on the sign shall be black. 2.4.6. Be removed within seven (7) days following the conclusion of the public meeting on the matter before the Planning and Zoning Commission or City Council as may be appropriate. Failure to remove the sign within the time frame as established under this provision may result in the imposition of a fine not to exceed fifty dollars ($50.00) per day for each day on which the sign is displayed in violation of this provision. 2.5. Applicability Of Approval: 2.5.1. A deviation to a platted building or setback line shall be subject to compliance with an approved site plan and shall be applicable only to the structure or structural improvement for which the deviation was approved. 2.5.2. A deviation shall not be valid if a building or structure for which a deviation has been granted is destroyed or damaged by fire, collapse, explosion or other casualty or act of God to the extent that the cost of restoration to the condition in which it was before the occurrence shall exceed fifty percent (50%) of the replacement cost of the building or structure at the time of destruction or damage. 2.5.3. In the event such damage or destruction is less than fifty percent (50%) of the replacement cost of the building or structure, the deviation shall be valid only if such restoration is started within six (6) months from the date of partial destruction and restoration proceeds and does not cease for a period of sixty (60) days and completion is accomplished within twenty-four (24) months from the date of partial destruction. 3. Permitted Obstructions: Those obstructions permitted through Section 6-2-3:3 (Permitted Obstructions in Required Yards) of Title 6 shall also be applicable to the platted setback line in accordance with limitations provided in that Section.
(Ord. No. 07-05, 1-2-2007; Ord. No. 13-129, § 7, 11-5-2013; Ord. No. 15-187, § 1, 11-17-2015)
Ask a question about Naperville law
Corpus searches the Naperville sections it holds and shows the ones that match, with their citations. Free, no sign-in.