§ 32-29 — Preliminary planned developments

Code of Ordinances of the Village of Palatine, Illinois (Codified through Ordinance No. O-113-26, enacted October 12, 2026. (Supp. No. 2, Update 2)) · Palatine Code of Ordinances § 32-29

Corpus is an independent public-information project, not the official City of Palatine website. Stable reference: corpuslaw.us/code/4547b13e-f6d3-4ea6-8809-915066f1ec2f

Sec. 32-29. - Preliminary planned developments.

(a) Application process. ..... (1) Preapplication submittal. Prior to filing a planned development application, the applicant shall provide the following: ..... a. Three copies of the plat of survey of the property in question. ..... b. Aerial photographs of the subject site. ..... c. Preliminary plans and sketches. ..... d. An outline summarizing the proposed development and the project timelines for the construction and completion of the proposed project. ..... e. Other site information, in such quantity as may be deemed necessary by either the administrator or applicant. ..... (2) Preapplication conference. ..... a. If requested within ten working days after receipt of documents required subsection (a)(1) of this section, the administrator shall schedule a preapplication conference with the applicant and planning staff. If such a conference is not requested, the standard project application process shall be followed. ..... b. The said conference shall be for the purpose of reviewing the applicant's proposal and to provide the applicant with a general indication of the feasibility of the proposal and required procedures. ..... (3) Preliminary planned development and rezoning application. Following the initial preapplication conference, a preliminary planned development and rezoning applications may be filed with the village, subject to the following: ..... a. Said application shall contain the following information: ..... 1. Filing fees, as required in the village fee schedule; ..... 2. Petition for hearing; ..... 3. Real estate interest disclosure form; ..... 4. Village of Palatine notice affidavit; ..... 5. Development narrative, including a description of how the proposed development relates to the village's comprehensive plan, surrounding zoning classifications, and surrounding land uses; ..... 6. Proof of ownership, including signatures of owners on the petition for hearing or on a statement attached to said form giving owner's consent of the petition; ..... 7. Plat of survey and legal description of the entire subject property; and ..... 8. Site plan and supporting documents. ..... b. The following materials may be required by the village, either as part of the application or as a condition of approval: ..... 1. Preliminary plat of subdivision; ..... 2. Tree survey; ..... 3. Tree preservation plan; ..... 4. Preliminary engineering plans, including: ..... (i) Existing conditions; ..... (ii) Topography; ..... (iii) Utility connections; ..... (iv) Utility mains and layouts; ..... (v) Grading plan; ..... (vi) Preliminary detention calculations; ..... 5. Soil borings and analysis report; ..... 6. Landscape plan; ..... 7. Architectural plans; ..... 8. Declarations, covenants, grants of easements and other limitations or restrictions; ..... 9. Development schedule, including marketing, construction, and estimated development completion timetables; ..... 10. Market analysis; ..... 11. Traffic analysis; ..... 12. Impact analysis to municipal systems; ..... 13. Developer information; ..... 14. List of proposed permitted uses within the development; ..... 15. The following quantitative data: ..... (i) Total number and type of dwelling units; ..... (ii) Parcel size; ..... (iii) Lot coverage of buildings and structures; ..... (iv) Total amount of open, and usable open space; ..... (v) Number of parking spaces; ..... 16. Lighting plan; ..... 17. Marketing materials; ..... 18. Economic impact analysis; ..... 19. Professional engineer's estimate of probable cost for all public and project improvements, submitted in a manner acceptable to the village engineer; ..... 20. Associated documentation required by any jurisdictional regulatory agency; and ..... 21. Any other information deemed necessary by the village. ..... (b) Administrative report. Within a maximum of 45 days following the submission of all documentation required in section 32-3(f) and subsection (a)(3) of this section, the administrator shall: ..... (1) Schedule a public hearing for the purpose of review of the preliminary planned development application and associated plans. ..... (2) Report to the applicant all concerns regarding submission of documents. ..... (3) Provide public notice of the public hearing pursuant to the zoning ordinance requirements. ..... (c) Public hearing and report. ..... (1) Public hearing. At the public hearing, the planning and zoning commission shall receive the administrator's report and solicit testimony from the general public. After due consideration, the planning and zoning commission shall vote, based on the standards of section 13.03 of Ordinance No. O-34-17, to take one of three actions: ..... a. Recommend approval of the preliminary planned development; ..... b. Not recommend approval of the preliminary planned development; ..... c. Recommend approval of the preliminary planned development with modifications and conditions. ..... (2) Report to village council. Within a maximum of 45 days of the completion of the public hearing, the planning and zoning commission shall report its findings to the village council together with the administrator's report. ..... (d) Actions by the village council. ..... (1) The village council shall consider the recommendations of the planning and zoning commission, public record, and the standards within section 13.03 of Ordinance No. O-34-17 and shall pass a motion to take one of three actions: ..... a. Approve the preliminary plan; ..... b. Do not approve the preliminary plan; ..... c. Approve the preliminary plan with modifications and conditions. ..... (2) Rezoning of the property shall not be considered by the village council at this preliminary planned development phase. The rezoning of the property to planned development shall not occur until the final planned development approval is granted. Preliminary planned development approval is advisory only, is not a final or binding decision, and shall not entitle the applicant to final planned development approval. ..... (e) Review fee. A plan review fee, based on 1.5 percent of total project improvement costs (which shall consist of, but not exclusively, curb and gutters, sidewalks, pavements, sanitary sewer system, storm sewer system, water distribution system, stormwater detention facilities, parkway trees, landscaping, street lights, plus soil erosion control measures) shall be as estimated by the design engineer and approved by the village engineer. .....

(Ord. No. O-31-88, § 1(13.04(a)—(c)(2), (d)—(g)), 3-14-1988; Ord. No. O-72A-98, § 10, 5-26-1998; Ord. No. O-60-06, § 16, 4-3-2006; Ord. No. O-34-17, 4-3-2017)