§ 8-207 — Stop work order

Code of Ordinances of the Village of Palatine, Illinois (Codified through Ordinance No. O-113-26, enacted October 12, 2026. (Supp. No. 2, Update 2)) · Palatine Code of Ordinances § 8-207

Corpus is an independent public-information project, not the official City of Palatine website. Stable reference: corpuslaw.us/code/a55d24a4-4764-49ca-b6a2-9eea0674b6c0

Sec. 8-207. - Stop work order.

(a) It shall be unlawful for any owner, agent, contractor, subcontractor or builder to make any departure from or violate: (1) Any ordinance or code of the village; (2) Any conditions attached to a special use ordinance, planned unit development ordinance, variation, or annexation agreement; (3) Any federal, state or other local law or ordinance; (4) Commit any fraud or make any misrepresentation or false statement in an application for a license or permit; or (5) Cause a nuisance or danger to the public health, safety or welfare. Any such departure from or violation of such ordinance, code, condition or threat to the public welfare or law shall operate to void the permit which has been issued for such work. (b) In addition to any and all other remedies the village may seek, the village manager, or his or her designee, without delay, shall issue a stop work order directing that all work shall cease and desist immediately until such time as the village manager has either received satisfactory evidence that the work to be performed will be done in accordance with such ordinance, codes, conditions, laws or the public welfare, or until the corporate authorities have acted on the matter pursuant to either paragraph (c) or (d). (c) The village manager, or his or her designee, may refer the matter of continuing the stop work order to the corporate authorities for further proceedings. The corporate authorities shall have the authority to: (1) Continue in effect the stop work order; (2) Lift the stop work order; (3) Impose additional requirements as conditions to lifting the stop work order; and/or (4) Any other relief consistent with the public welfare. (d) Any person aggrieved by the decision of the village manager, or his or her designee, in regard to the issuance of a stop work order or refusal to rescind the same shall have the right to appeal to the corporate authorities. Such appeal shall be taken by filing with the village manager, or his or her designee, within five days after receipt of a stop work order or after the village manager's, or designee' s, refusal to rescind such an order, a written statement under oath setting forth specifically the grounds for appeal. The corporate authorities shall appoint a hearing body to be composed of the mayor or the mayor's designee and two council members who shall thereupon set the time and place for a hearing of such appeal and notice of such hearing shall be given to the appellant. The hearing body shall make a recommendation to the corporate authorities which shall render a decision on such appeal which shall be final. Any appeal from a decision of the corporate authorities shall be made directly to the Circuit Court of Cook County pursuant to the Administrative Review Act (735 ILCS 5/3-101, et seq.). (e) All costs and expenses including but not limited to court reporters fees and attorneys' fees incurred by the village in connection with any appeal of a stop work order shall be taxed to the appellant and shall be paid by the appellant as a condition to reinstatement of the permit. (f) The authority to issue a stop work order shall be in addition to any other relief available to the village.

(Code 1976, § 6-92; Ord. No. O-111-24, exh. A(6-92), 12-2-2024; Ord. No. O-47-25, § 1(Exh. A), 5-19-2025)