Sec. 18-28. - Building demolition.

(a) Before any building or structure is demolished voluntarily or as required by code, a demolition permit shall be obtained. A demolition permit shall be issued only to an approved demolition contractor licensed by the city or to an applicant who is the owner of the single-family residential building or structure to be demolished and who is the owner of the property upon which such building or structure is located. (b) When a building demolition permit is issued, the permit shall comply with the following: (1) The demolition site shall be fenced or barricaded and posted "No Trespassing" until demolition work is completed. (2) Prior to starting demolition work, the permittee shall notify the appropriate utilities in order that all gas, water, electrical and sanitary sewer lines are properly disconnected and securely capped and sealed when applicable. An inspection of capped sewer and water lines will be required before backfilling of the demolition site. If septic tanks, cesspools, or other buried storage tanks are present on the demolition site, these shall be filled with dirt or sand and inspected. (3) All demolition debris, including basement footings, floors, walls and/or stem walls, shall be removed from the demolition site. (4) Upon completion of the demolition work any openings or excavations on the demolition site shall be backfilled with dirt or sand to at least six inches above existing grade to allow for settling. A final inspection of the demolition site by the building official will be required. Alternate methods of backfilling may be approved by the building official. When work is completed, the site shall be seeded with grass to prevent erosion. (5) All demolition work shall be completed within 60 days of the date of issuance of the demolition permit.

(Ord. No. 2861-2020, § 1, 3-17-20)