Sec. 27-104. - Costs and scheduling of make ready work.
(a) The cost of all make ready work, as such cost is identified by the city, shall be paid prior to issuance of any permit. After receipt of such payment and issuance of a permit by the city, the city will cause the make ready work to be performed in accordance with this article and pursuant to a schedule that avoids conflict or interference with the city's prior work commitments and regular business operations. The make ready work will be completed within 120 days of the completed application being submitted to the city, unless otherwise mutually agreed to by the city and wireless services provider. (b) Applicants shall pay for engineering work performed by the city, which includes, but is not limited to, analysis, field survey or inspection of the proposed wireless facilities. In addition, applicants shall pay all actual and documented costs (to the extent not paid pursuant to subsection (a) above), when incurred and billed, for the preparation of engineering documentation or work orders and drawings, that may be necessary to accommodate the wireless facilities, whether occurring prior to the placement of any wireless facilities on city poles or wireless support structures, or occurring subsequent to the placement of any wireless facilities on city poles or wireless support structures in connection with any post-construction inspection(s) to determine whether the wireless facilities have been attached properly in accordance with the application and all applicable permits. The city shall provide the applicant with an invoice for all actual and documented costs incurred for such additional work. (c) Applicants shall be responsible for entering into an agreement with any existing other attaching entities to reimburse them for any costs that they incur in rearranging or transferring their facilities to accommodate the applicant's attachment(s). (d) Applicants shall pay the actual and documented costs incurred by the city to upgrade or replace city poles or wireless support structures to which the applicant's facilities are attached if the upgrade or replacement is required solely by the addition or modification of the applicant's facilities or equipment, and to pay its proportionate share of the costs incurred by city to upgrade or replace city poles or wireless support structures if the upgrades or replacements directly benefit the applicant and other users to such city poles or wireless support structures and are made to meet the city's service needs, are made at the request of the applicant or an additional attaching party, or are made as a result of a governmental order or regulation.
(Ord. No. 2853-2019, § 2, 10-15-19)
Ask a question about Garden City law
Corpus searches the Garden City sections it holds and shows the ones that match, with their citations. Free, no sign-in.