Sec. 5-2202. - Permit required, permit contents.
(a) At least 45 days, prior to the construction, reconstruction or rerouting of any electric lines, poles and appurtenances, with voltages equal to or in excess of 69 KV, but not including 230 KV or greater if the line is over five miles in length, on city right-of-way or public easements and private easements and right-of-way of the franchised utility, the franchised utility shall submit an application for a permit to the city clerk. (b) If such permit application has not been approved or disapproved, or a public hearing on the permit application scheduled for a future date, within 60 days from submission of the permit application, the permit shall be deemed approved and valid. (c) A franchised utility shall not construct, reconstruct, or reroute an existing or new electric line with voltages equal to or in excess of 69 KV up to, but not including 230 KV if the line is over five miles in length, upon the public right-of-way or public easements and private easements and right-of-way of the franchised utility without a permit approved by the city commission. Such permit application shall include the information below for the preferred and at least two other alternative constructions the franchised utility has considered. Upon request of the franchised utility, the city commission may waive the requirement for application information on alternative constructions. (d) The permit application shall include the following information: (1) A general description of the proposed electric line design, including wire configuration; average, maximum and minimum current expected; projected electromagnetic fields; length of the line; number of angle and dead end structures; right-of-way width and total acres of right-of-way needed; number of buildings (homes, schools, playgrounds) within 100 feet of the line; number of highway and river crossings; (2) A map showing the approximate alignment and proposed pole locations, including the size and height of poles; (3) The preferred construction schedule and timeline for construction; (4) The estimated cost of the preferred construction and its alternatives; (5) The justification for the preferred route with all criteria used in making that selection from among the alternatives examined; (6) The estimate by the franchised utility of the general effects on adjacent property owners and the public at large from the proposed construction; (7) Such other information as may be appropriate and required by the city from time to time.
(Code 2018, § 5-2002; Ord. No. 6423)
Ask a question about Lawrence law
Corpus searches the Lawrence sections it holds and shows the ones that match, with their citations. Free, no sign-in.