Sec. 105-27. - Construction of facility; notification of final completion date.
(a) Construction of facility. Construction pursuant to a permit under this chapter must commence no later than 12 months after issuance of the permit and thereafter be diligently pursued to completion, provided that the deadline to commence construction shall be extended for any delays attributable to the lack of commercial power or communications facilities at the site or by mutual agreement of the applicant and the city. (b) Notification of final completion. Permittee shall notify the city in writing of the notification of final completion date of the facility and said notification shall be received by the city no later than 30 days after final completion. Said notification shall contain a statement from the permittee that the facility was constructed as approved and permitted in accordance with the issued SWF permit.
(Ord. No. 131, 2018, Exh. B, 1-8-19)