§ 17.4 — PRELIMINARY PLAT

Code of Ordinances, City of Shreveport, Louisiana (Supp. No. 85, Update1: codified through Ordinance No.150, 2025 adopted December 9, 2025) · Shreveport Unified Development Code § 17.4

Corpus is an independent public-information project, not the official City of Shreveport website. Stable reference: corpuslaw.us/code/79f91821-ca60-4fbb-97da-d35410a64528

17.4 - PRELIMINARY PLAT

A preliminary plat is required only for major subdivisions. A preliminary plat is not required for an administrative or minor subdivision. A. The purpose of the preliminary plat is to develop a general design for the construction of the subdivision and to assure conformity with the Master Plan and the appropriate relationship to both existing and anticipated future development surrounding the proposed subdivision. B. Prior to submitting a preliminary plat to the Metropolitan Planning Commission for approval, the subdivider or his representatives will meet with the Executive Director to review the plan. The subdivider will submit, in addition to the preliminary plat requirements, an improvement plan that includes information, including drawings and specifications, for the construction and installation of required improvements. If the subdivider proposes to develop the land within only a portion of the preliminary plat, the improvement plan may include only that portion to be developed at the time. The review must take into consideration, in addition to the requirements of these regulations, conformance with the applicable standards and regulations of the City and other applicable agencies. C. The Executive Director will prepare a recommendation on proposed improvements and exceptions to accompany the submission of the preliminary plat to the Metropolitan Planning Commission. D. The application for a preliminary plat and the Executive Director recommendation must be submitted to the Metropolitan Planning Commission no later than the deadline dates annually posted by the Commission. The application must be accompanied by two copies of the preliminary plat and all submittal requirements. E. Neighborhood Participation Plan Some applications for a preliminary plat, with the exception of applications listed below, may be required to include a Neighborhood Participation Plan (NPP) report. Until all required (NPP) documents are submitted to MPC staff, the application for a preliminary plat will not be deemed complete. All requirements for the (NPP) program are described in Section 15.4 (Neighborhood Participation Plan). Exceptions of applications that do not have to participate in the Neighborhood Participation Meeting Program include when: 1. The subject property has been the subject of a zoning change within the previous 12 months of application submittal. 2. The subject property is a part of an approved Planned Unit Development or conditional zoning district. 3. The number of lots being considered for approval is less than 30 units. F. After receipt of a complete application, the Metropolitan Planning Commission will consider the preliminary plat at a public hearing in accordance with Section 15.3 (Public Hearing). Notice for the public hearing must be in accordance with Section 15.2 (Notice). G. Within 60 days of the close of the public hearing, the Metropolitan Planning Commission must evaluate the preliminary plat based upon the evidence presented at the public hearing, and approve, approve with conditions, or deny the preliminary plat. The Metropolitan Planning Commission decision must include a description of the public or private improvements required. The Metropolitan Planning Commission may deny the plat if there are key errors or omissions or the Commission may extend the time to make a decision to remedy such errors or omissions. The applicant may also request an extension of time. H. Approval of the preliminary plat constitutes authorization for the applicant to proceed with preparation of the improvement plans in accordance with the approved preliminary plat and any conditions specified. I. The preliminary plat approval expires if a complete application for approval of a final plat has not been filed within one year after the date the Metropolitan Planning Commission grants preliminary plat approval. As part of the approval of the preliminary plat, the Metropolitan Planning Commission may extend this period of validity. An extension of this one year validity period may also be granted by the Executive Director if the applicant requests an extension in writing prior to the expiration date of the approval. J. Approval of a final plat that contains only a portion of the area depicted in the preliminary plat will extend the effective approval period for the balance of the property for one year from that date. However, in order to qualify for such extensions, a phasing plan is required as part of the preliminary plat and must be approved by the Metropolitan Planning Commission. K. Approval or denial of a preliminary plat may be appealed to the City Council for a preliminary plat located within the boundaries of the City of Shreveport.

(Ord. No. 191, 2019, § 26, 1-14-20; Ord. No. 192, 2019, § 9, 1-14-20; Ord. No. 196, 2020, § 13, 1-12-21; Ord. No. 149, 2024, § 18, 11-8-24)